Karnataka CM Shivakumar seeks NBWL nod for Sharavathi, Mekedatu projects
Synopsis
Key Takeaways
Karnataka Chief Minister D.K. Shivakumar on Thursday, 22 October met Union Environment, Forest, and Climate Change Minister Bhupender Yadav at Paryavaran Bhawan in New Delhi, urging the Centre to fast-track approvals from the Standing Committee of the National Board for Wildlife (NBWL) for two critical infrastructure projects — the Sharavathi Pumped Storage Project and the Mekedatu balancing reservoir and drinking water project.
Sharavathi Project: Where Approval Stands
Shivakumar told the minister that the Sharavathi proposal was last taken up at the 89th meeting of the NBWL Standing Committee on 28 February this year. At that meeting, the technical committee had directed the state government or the user agency to address specific queries and submit a technical report from the National Institute of Advanced Studies (NIAS), Bengaluru.
The Karnataka government has since fulfilled both conditions, submitting the NIAS technical report along with responses to all queries raised by the Standing Committee. Shivakumar urged Yadav, in his capacity as Chairman of the NBWL Standing Committee, to expedite the examination and issue recommendations.
Mekedatu: Survey-Stage Clearance Sought
On the Mekedatu project, Shivakumar confirmed that a proposal seeking permission to drill 20 boreholes for geotechnical investigations within the Cauvery Wildlife Sanctuary was submitted to the Union Ministry on 1 July. The investigation would cover a total area of 0.0000352 hectares within the sanctuary.
The Chief Minister was careful to clarify that the proposal covers only survey and investigation activities and does not seek diversion of any protected-area land at this stage. The Ministry had, reportedly, sought documents related to the status of petitions pending before the Supreme Court of India concerning the project; the state government said it would furnish the required information shortly.
Western Ghats ESA Notification: Karnataka Pushes Back
Shivakumar also pressed Yadav not to finalise the seventh draft notification — issued by the Ministry on 27 July — that proposes to declare parts of the Western Ghats as an Ecologically Sensitive Area (ESA) based on the Kasturirangan Committee report.
He disclosed that he had already written to Prime Minister Narendra Modi on 25 September, requesting that no final decision be taken until the state government's High-Level Committee (HLC) submitted its report and a full physical survey was completed within one year. The Chief Minister urged that any further action be undertaken in consultation with the Karnataka government after both exercises are concluded.
Belagavi Sugar Factory: Exemption Requested
Separately, Shivakumar requested the Centre to exclude the Eco Cane Sugar and Energy Ltd. sugar factory in Belagavi from the proposed eco-sensitive zone. He argued that the factory commenced operations before 2016 and should therefore be exempt from ESA restrictions. The plant employs around 500 workers, with approximately 5,000 families depending on it for their livelihoods — a humanitarian dimension, he said, that the Centre must weigh before finalising the notification.
All three requests will now await a response from the Union Ministry, with the NBWL Standing Committee's next meeting date yet to be announced.