Will the Udangudi Thermal Power Plant Begin Power Generation by Next Summer?

Synopsis
Key Takeaways
- Udangudi Thermal Power Plant set to begin operation by summer 2024.
- Project will add 1,320 MW to Tamil Nadu's power grid.
- Construction of Unit 1 is over 90% complete.
- Challenges included skilled labor shortages and technical issues.
- Designed to enhance efficiency and reduce emissions.
Chennai, July 19 (NationPress) The Udangudi supercritical thermal power plant located in Thoothukudi district, Tamil Nadu, is projected to kick off its power generation by next summer, with rapid advancements being made on the first unit.
This ambitious Rs 13,076 crore project, which consists of two 660 MW units, aims to greatly enhance Tamil Nadu's electricity supply during periods of peak demand.
Tamil Nadu Generation and Distribution Corporation (Tangedco) Managing Director J. Radhakrishnan reported that construction on Unit 1 is over 90% complete.
Initially, the goal was to have the first unit operational by September, but the MD indicated a potential delay, stating efforts are now concentrated on ensuring electricity generation starts by the year's end.
“Work is proceeding at full pace to ensure everything is ready before next summer,” said Radhakrishnan. “Once Unit 1 is fully functional, Unit 2 will be ready within the next four months.”
He noted that the installation of essential components, including boilers, turbines, and the power house, is finished. Work on the ash handling section and securing fire safety certification is currently being expedited.
During test trials of Unit 1, approximately 10 technical issues were identified and resolved. Radhakrishnan also highlighted that a significant cause of the delay was the shortage of skilled labor.
The Udangudi Thermal Power Project was first announced in 2012 to meet Tamil Nadu's increasing electricity demands. However, due to delays in approvals and administrative processes, construction only began in 2017.
The project spans a 360-acre site near the coastal town of Udangudi and is designed as a supercritical thermal plant using imported coal, aiming to enhance efficiency and lower emissions compared to traditional coal plants.
Once operational, the plant is expected to contribute 1,320 MW of power to the state grid, providing essential support during peak demand seasons, particularly in summer months when electricity consumption surges due to air conditioning and agricultural needs.
Officials are hopeful that once fully operational, the project will significantly strengthen Tamil Nadu's power infrastructure and ensure energy security for the future.