Chamoli tunnel rescue: 19 of 22 trapped workers saved, 7 dead; CM Dhami inspects site
Synopsis
Key Takeaways
Uttarakhand Chief Minister Pushkar Singh Dhami on Friday, 14 August conducted an on-site inspection of the disaster-hit THDC tunnel in Chamoli district, where a cave-in trapped more than two dozen workers at the Vishnugad-Pipalkoti Hydroelectric Project site in Pipalkoti. According to the Chamoli District Magistrate, 19 of the 22 workers confirmed trapped have been rescued, while search operations for the remaining three continue. Seven deaths have been reported in connection with the incident.
What Triggered the Disaster
The incident occurred inside the TRT tunnel of THDC's Vishnugad-Pipalkoti Hydroelectric Project, an under-construction structure approximately 3 kilometres long. A subsidence — or cave-in — in a section spanning roughly 1.50 km of the tunnel caused a sudden influx of water and debris, trapping workers who were inside at the time. Several of those trapped were evacuated on Thursday night, with rescue efforts continuing through Friday.
CM Dhami's On-Ground Inspection
Chief Minister Dhami entered the affected tunnel personally to assess the extent of damage and take stock of the rescue mission's progress. He was briefed by officials and rescue teams on the challenges being faced in reaching the remaining trapped workers. Following the briefing, Dhami issued direct instructions to officials to ensure no lapses at any level.
In a post on X, Dhami stated: 'While reviewing the progress and challenges of the operation on the ground, I directed the officials to ensure no lapses at any level in the rescue efforts and to utilize all available resources to their full capacity. Evacuating every worker safely is our topmost priority.'
Multi-Agency Rescue Operation
The Chief Minister stressed the need for seamless coordination among all agencies deployed at the site, including the National Disaster Response Force (NDRF), State Disaster Response Force (SDRF), Indo-Tibetan Border Police (ITBP), and the local police. He directed that the operation be conducted at 'war footing' until all remaining workers are accounted for.
Condition of Rescued Workers
Injured workers who were evacuated have been shifted to the District Hospital in Gopeshwar, where a dedicated team of doctors and Health Department personnel are providing treatment. Authorities have not yet disclosed the nature or severity of injuries sustained by the rescued individuals.
What Comes Next
With three workers still unaccounted for inside the tunnel, rescue operations are expected to continue around the clock. The incident has drawn attention to safety protocols at hydroelectric project construction sites in Uttarakhand's fragile Himalayan terrain — a region that has seen repeated tunnel and infrastructure disasters in recent years. Authorities have not yet announced a formal inquiry into the cause of the subsidence.