HC extends Abhishek Banerjee office demolition stay to Dec 15
Synopsis
Key Takeaways
The Calcutta High Court on Thursday extended the interim stay on the demolition of the Trinamool Congress office at Amtala in South 24 Parganas district of West Bengal until 15 December. The office was used by Abhishek Banerjee, the party's general secretary and Diamond Harbour Lok Sabha member. The order, passed by a single-judge bench in Kolkata, is the second time the court has extended its protection over the structure.
Key Developments in Court
The matter was heard again on Thursday before the single-judge bench of Justice Suvra Ghosh. At the end of the hearing, the bench extended the interim stay to 15 December.
Justice Ghosh first granted the interim stay on 16 August, initially valid until 18 September. It was later extended to 30 November, and Thursday's order pushes it further into December.
How the Demolition Began
The case traces back to 17 May, when a person named Sushant Mondal filed a complaint alleging that the Amtala office had been illegally constructed. The district administration acted on that complaint and began demolition proceedings in July.
On 18 July, part of the office was demolished. According to the source account, demolition work resumed the following day. Banerjee, a nephew of Mamata Banerjee, then moved the Calcutta High Court seeking a stay on the demolition.
Arguments Raised by Banerjee's Counsel
Banerjee's counsel argued that the complaints of illegal construction related to plot numbers 509 and 512 at the site. However, the counsel said the construction on plot number 507, which housed his client's office, was the one demolished.
The counsel also alleged that the administration started the demolition without giving Banerjee an opportunity to present his side. In addition, he sought compensation from the administration for the portion of the structure already demolished.
Ownership of the Property
The office is registered in the name of a corporate entity, Leaps & Bounds Private Limited, which is linked to the Banerjee family. The demolition notice issued by the administration was also addressed to this company.
This detail places the dispute between the district administration and a private company, even as the structure functioned as a political office used by one of the party's most prominent leaders.
What Happens Next
The stay means no further demolition can take place at the Amtala site until at least 15 December. The court is expected to take up the matter again before that date. At the next hearing, the questions of plot identification, procedural fairness and Banerjee's demand for compensation are likely to be central to the dispute.