Has Delhi CM Ordered ACB Investigation into Barapullah Road Phase-III Project Irregularities?

Synopsis
Key Takeaways
- ACB investigation into the Barapullah project initiated.
- Previous AAP government criticized for negligence.
- Project cost now estimated at Rs 1,330 crore.
- 87% of the construction work has been completed.
- Permits for tree removal expected soon to expedite progress.
New Delhi, July 28 (NationPress) The Chief Minister of Delhi, Rekha Gupta, has initiated an investigation by the Anti-Corruption Branch concerning the irregularities associated with the ongoing Barapullah Elevated Road Phase-III project, which has encountered significant cost overruns and delays.
During a meeting of the Expenditure Finance Committee on Monday, the CM assessed the project's status and acknowledged the pressing issues raised about the Public Works Department’s (PWD) negligence and the extensive delays.
The Chief Minister directed senior officials to guarantee the project's prompt completion, noting that a payment of Rs 175 crore to the contractor became necessary because the preceding government had barred the company from carrying out the work.
CM Gupta referred to the project as another instance of corruption and negligence under the previous Aam Aadmi Party (AAP) administration.
She pointed out that the project, initially set for completion in October 2017, faced multiple delays and eventually went to arbitration.
The ruling favored the contractor with an award of Rs 120 crore. When the payment was withheld, the contractor sought recourse from the High Court, which in May 2023 mandated the PWD to pay Rs 175 crore, including interest and GST. This amount was eventually disbursed during the term of then PWD Minister Atishi.
CM Gupta criticized the AAP government for failing to file a review petition or take action against negligent officials, emphasizing that the payment adversely affected other PWD projects.
She also revealed that the contractor had initially proposed to resolve the dispute for Rs 35 crore, but this offer was disregarded, leading to escalation to the High Court.
The elevated road is set to extend from Barapullah Nallah to Mayur Vihar Phase-III via Sarai Kale Khan.
According to PWD Minister Pravesh Verma and officials, the project is set to gain momentum as the necessary permissions for tree removal along the route are anticipated soon.
The Delhi Cabinet sanctioned the project in September 2011, allocating Rs 1,260.63 crore in December 2014.
Construction commenced in April 2015, with a designated completion timeline of 30 months.
The original estimate for the project was Rs 1,260.63 crore, of which Rs 1,238.68 crore has been expended thus far. The total projected cost has now escalated to Rs 1,330 crore.
Currently, 87 percent of the work is completed. The anticipated permissions for early tree removal are expected shortly, leading to a boost in project progress.
For the fiscal year 2025–26, Rs 150 crore has been earmarked, with Rs 86.43 crore spent by June 2025.