Dungarpur-Ratlam rail line: 646 hectares acquired, ₹243 crore spent
Synopsis
Key Takeaways
The 189-km Ratlam-Banswara-Dungarpur new railway line, sanctioned at an estimated cost of ₹2,083 crore, is making measured progress with 646 hectares of land acquired out of the 1,736 hectares required, Union Railway Minister Ashwini Vaishnaw told the Rajya Sabha in a written reply on 7 August. A total expenditure of ₹243 crore has been incurred on the project up to March 2026.
Project Structure and Funding
The line is being executed on a 50:50 cost-sharing basis between the Ministry of Railways and the Rajasthan Government. Under this arrangement, the state is responsible for providing land free of cost — a condition that has historically been a bottleneck for rail projects in the region. With roughly 37% of the required land acquired so far, land procurement remains the critical path for the project's timeline.
New DPR Sanctioned for Broader Connectivity
To further strengthen rail access in the Banswara region, the Railways has sanctioned a Detailed Project Report (DPR) for a proposed 380-km Nimach-Banswara-Dahod-Alirajpur-Nandurbar new railway line. The project will be considered for formal sanction only after the DPR is complete and consultations are held with stakeholders — including the concerned state governments, NITI Aayog, and the Ministry of Finance.
Rajasthan's Railway Budget: A 15-Fold Rise
Minister Vaishnaw highlighted a sharp escalation in railway investment in Rajasthan. The state's annual railway budget allocation has surged from an average of ₹682 crore during 2009-14 to ₹10,228 crore in 2026-27 — nearly 15 times higher. Track commissioning has also accelerated: 3,886 km of new track was commissioned between 2014 and 2026, averaging 324 km per year, compared with 798 km at an average of 160 km annually during the preceding five-year period.
32 Projects Under Implementation Across the State
As of 1 April 2026, a total of 32 railway infrastructure projects — covering 3,447 km and involving an investment of ₹47,498 crore — are under implementation in Rajasthan. These include 15 new lines, 5 gauge conversion projects, and 12 doubling projects. Of these, 1,322 km have been commissioned, and ₹23,245 crore has been spent up to March 2026.
Recently completed projects include the Bina-Kota doubling, Dausa-Gangapur City doubling, Phulera-Degana doubling, Alwar-Bandikui doubling, and the Jaipur-Churu gauge conversion. Major ongoing works include the Pushkar-Merta, Taranga Hill-Abu Road, Ramganjmandi-Bhopal, Sawai Madhopur-Jaipur doubling, Luni-Bhildi doubling, and the Nagda-Mathura third and fourth line projects.
Challenges Ahead
Vaishnaw acknowledged that timely completion depends on several factors beyond the Railways' direct control, including land acquisition, forest and statutory clearances, shifting of utilities, geological conditions, law and order, and the working season available at project sites. For the Dungarpur-Ratlam corridor — which passes through tribal-dominated terrain — these constraints are particularly relevant. The project's trajectory will ultimately hinge on how quickly Rajasthan can complete the remaining land handover.