Lower Subansiri Dam safe, says Assam Minister after site inspection
Synopsis
Key Takeaways
Assam Education and Information Technology Minister Ranoj Pegu on Monday, 3 August visited the 2,000 MW NHPC Lower Subansiri Hydroelectric Project at Gerukamukh and declared the dam structurally sound, seeking to calm fears among downstream communities rattled by recent flooding across the state.
What the Inspection Found
Pegu reviewed the dam structure, reservoir, control room, and the Early Warning System installed at the facility. He also held detailed discussions with NHPC engineers on operational mechanisms and flood management protocols currently in place.
According to the minister, the 116-metre-high dam has its reservoir filled to 92 metres, maintaining a 15-metre flood cushion to absorb excess monsoon inflows and moderate downstream flooding. Water is currently being released at approximately 3,800 cubic metres per second (cumecs) in a regulated manner.
Peak Inflow During July Rains
Pegu noted that the project recorded its highest inflow of nearly 13,800 cumecs during a heavy rainfall spell on 13 July. Of this, approximately 12,500 cumecs was discharged in a controlled manner, while the remaining volume was retained in the reservoir to reduce downstream flood intensity — a figure that officials say demonstrates the dam's buffering capacity under stress conditions.
What the Government Said
'After personally inspecting the project and interacting with the engineers, I am convinced that the Lower Subansiri Dam is safe. The release of water is carefully regulated, and all operations are being carried out under the prescribed safety protocols,' Pegu said.
He added that reservoir levels are under continuous surveillance and that the dam is being operated in line with guidelines set by the National Dam Safety Authority.
Reassurance for Downstream Districts
Pegu specifically addressed residents of downstream districts including Dhemaji, Lakhimpur, and Majuli, stating there was no cause for panic. He underlined that the project has the capacity to temporarily store excess monsoon inflows and release water in a calibrated manner to help mitigate flood risks.
He reiterated that the safety of downstream communities remains the government's foremost priority and that all agencies are working in close coordination. With the monsoon season still active, the dam's operations will remain under close watch in the weeks ahead.