Kishan Reddy shares Kazipet station redevelopment update

Share:
Audio Loading voice…
Kishan Reddy shares Kazipet station redevelopment update

Synopsis

Union Minister G. Kishan Reddy posted a detailed Kazipet station redevelopment update on November 1, listing five completed works — including the RPF building and South ESS — and nine ongoing components such as the air concourse, metro link, and north-side facilities under the Amrit Bharat Station Scheme.

Key Takeaways

Five works completed at Kazipet station: RPF building, Kazipet-end FOB, South station ground floor (departure and arrival), South basement, and South Electrical Substation.
Nine components in progress , including the South station building upper floors, North multi-level car parking, North station building, North basement, air concourse, Hyderabad-end FOB, cover-over-platform works, FOBs with travelators on Platforms 1 and 10, metro connectivity, and platform flooring.
Kazipet is a key Telangana railway junction being upgraded under the Amrit Bharat Station Scheme , which covers over 1,300 stations nationally.
The metro connectivity component reflects Indian Railways' multimodal integration push, linking intercity and urban rail networks.
Kishan Reddy , also BJP Telangana state president, posted the update with four on-site images on November 1, 2026 .

A major railway junction in Telangana is taking shape — and Union Coal and Mines Minister G. Kishan Reddy posted a detailed progress scorecard for the Kazipet station redevelopment on Sunday, November 1, 2026, laying out what has been built and what is still rising.

What has already been handed over at Kazipet

Five components are now in the 'completed' column. The Railway Protection Force (RPF) building is operational, giving the security wing a dedicated facility at the junction. The Kazipet-end Foot Over Bridge (FOB) is done, giving passengers a safe, direct crossing. On the southern flank, the South station building's ground floor — covering both departure and arrival areas — has been finished, alongside the South basement and the South Electrical Substation (ESS), which underpins power supply for the modernised facility.

The construction front still active

The larger, more complex works remain in motion. The South station building above ground-floor level is progressing, while the entire northern side — the North multi-level car parking, the North station building, and the North basement — is under active construction. The project's most ambitious element, an air concourse connecting both sides of the station, is in progress, as is a second Hyderabad-end FOB. Cover-over-platform works, FOBs with travelators along Platforms 1 and 10, metro connectivity works, and platform flooring improvements round out the ongoing list.

Amrit Bharat Scheme and what Kazipet represents

Kazipet's transformation sits within the Amrit Bharat Station Scheme, launched in 2023, which targets the redevelopment of over 1,300 stations across India with upgraded passenger amenities, multimodal integration, and modern infrastructure. Kazipet is a strategically important junction in Telangana, lying on key trunk routes, and its redevelopment — with travelators, a metro link, and a multi-level car park — signals a step change from legacy station design toward airport-style passenger experience. The metro connectivity component, in particular, reflects Indian Railways' broader push to knit urban rail and intercity networks into a single seamless system.

As the BJP's Telangana state president, Kishan Reddy's periodic progress updates on projects like Kazipet serve a dual function: accountability on infrastructure delivery and a visible marker of central government investment in the state. The post's granular breakdown — completed versus in-progress — is more operational dispatch than political statement, but it lands at a time when Telangana's infrastructure pipeline is closely watched by commuters and the state's political audiences alike.

The completion of the air concourse and the northern works will mark the real test of the project's ambition — when both ends of the station finally meet in the middle.

Point of View

Telangana, where the party is in opposition. The Amrit Bharat Station Scheme, covering 1,300-plus stations, is one of the Modi government's most visible infrastructure bets, and regular constituency-level updates serve as proof of execution. The inclusion of metro connectivity and travelator-equipped FOBs at Kazipet signals that the scheme is moving beyond cosmetic upgrades toward genuine multimodal ambition. How quickly the air concourse and north-side works are completed will determine whether Kazipet becomes a template or a cautionary tale for the broader programme.
NationPress
1 Nov 2026

Frequently Asked Questions

What works have been completed at Kazipet railway station?
The RPF building, Kazipet-end Foot Over Bridge, South station building ground floor (including departure and arrival areas), South basement, and South Electrical Substation have been completed.
What is the Amrit Bharat Station Scheme?
The Amrit Bharat Station Scheme was launched in 2023 to redevelop more than 1,300 railway stations across India with modernised passenger facilities, improved infrastructure, and multimodal connectivity.
What is still under construction at Kazipet station?
Works in progress include the South and North station buildings, North multi-level car parking, North basement, air concourse, Hyderabad-end FOB, cover-over-platform works, FOBs with travelators on Platforms 1 and 10, metro connectivity, and platform flooring improvements.
Why is metro connectivity being added to Kazipet station?
Metro connectivity is part of Indian Railways' broader push to integrate intercity rail with urban transit systems, making Kazipet a multimodal hub for Telangana commuters.
Who is G. Kishan Reddy and why is he posting about Kazipet?
G. Kishan Reddy is the Union Minister of Coal and Mines and BJP's Telangana state president. He regularly posts infrastructure progress updates for projects in Telangana, where the party is in opposition to the state government.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 3 months ago
  2. 3 months ago
  3. 4 months ago
  4. 4 months ago
  5. 5 months ago
  6. 5 months ago
  7. 5 months ago
  8. 5 months ago
Google Prefer NP
On Google