PMK's Anbumani urges Railways to fast-track 19 Tamil Nadu projects worth ₹27,282 crore

Share:
Audio Loading voice…
PMK's Anbumani urges Railways to fast-track 19 Tamil Nadu projects worth ₹27,282 crore

Synopsis

Only 24 km of track laid out of 811 km planned, and less than 10 per cent of ₹15,653 crore spent on new lines alone — PMK's Anbumani Ramadoss has laid bare the scale of Tamil Nadu's railway stall in a letter to Union Minister Ashwini Vaishnaw, demanding a special monitoring committee and monthly progress reports to rescue two decades of unfinished projects.

Key Takeaways

PMK president Anbumani Ramadoss wrote to Railway Minister Ashwini Vaishnaw on 10 November 2026 over 19 stalled rail projects in Tamil Nadu .
The projects — 8 new lines, 8 track-doublings, 3 gauge conversions — carry a combined cost of ₹27,282 crore , with only ₹8,811 crore (under 33%) spent so far.
Of 811 km of new railway lines planned, only 24 km (about 2.95%) has been completed; expenditure is under 10% of the ₹15,653 crore estimated cost.
The Union Government allocated ₹7,611 crore for Tamil Nadu in 2026–27 , but Anbumani argues higher budgets have not yielded ground-level progress.
PMK has proposed a special monitoring committee with Union, state, and district officials to submit monthly progress reports and fast-track land acquisition.

PMK president Anbumani Ramadoss has written to Union Railway Minister Ashwini Vaishnaw, urging him to expedite 19 long-pending railway infrastructure projects in Tamil Nadu, warning that prolonged delays are hampering connectivity and economic growth across the state. The letter, dispatched on Tuesday, 10 November 2026, highlights a sharp gap between financial allocations and actual progress on the ground.

The Scale of Delay

According to figures cited by Anbumani in his letter, the 19 stalled projects — comprising eight new railway lines, eight track-doubling works, and three gauge conversion projects — remained incomplete as of 1 April 2026. Their combined estimated cost stands at ₹27,282 crore, yet expenditure so far amounts to only ₹8,811 crore, representing less than 33 per cent of the total projected investment.

Anbumani noted that a significant portion of even that spending has been eroded by escalating construction costs and inflation, further undermining real progress on the projects.

New Railway Lines: A Near-Standstill

The situation is particularly stark for eight sanctioned new railway line projects covering 811 kilometres, with a projected investment of ₹15,653 crore. Despite several of these projects having been announced more than two decades ago, cumulative expenditure stands at just ₹1,514 crore — under 10 per cent of estimated cost. Only 24 kilometres of new track, approximately 2.95 per cent of the proposed network, has actually been laid.

Anbumani identified inadequate project-specific funding and delays in land acquisition as the two primary structural bottlenecks blocking implementation.

Funding Gap Despite Record Allocation

While welcoming the Union Government's allocation of ₹7,611 crore for Tamil Nadu in the 2026–27 financial year, Anbumani cautioned that increased budgetary commitments have not translated into meaningful on-ground delivery. He argued that the widening gap between announced outlays and actual construction activity was undermining public confidence in central railway investment promises.

This comes amid broader concerns across several southern states about equitable distribution of railway capital expenditure relative to the North-South ratio of network expansion.

What PMK Has Proposed

Anbumani has called for the creation of a special monitoring committee comprising representatives from the Union and Tamil Nadu governments, railway officials, technical experts, and district administrations. The committee, he suggested, should coordinate funding, accelerate land acquisition, and submit monthly progress reports to identify bottlenecks and ensure time-bound implementation.

He also stressed that extending railway connectivity to tier-II cities and underserved regions was critical for industrial growth, investor attraction, and improved passenger services across the state.

What Happens Next

The Railway Ministry is yet to formally respond to the letter. With the 2026–27 budget cycle already under way, observers say a structured monitoring mechanism — if accepted — could become the template for similar stalled projects in other states. The pace of the Centre's response to Anbumani's proposal is likely to shape PMK's political posture on railway infrastructure heading into the next electoral cycle in Tamil Nadu.

Point of View

₹15,653 crore sanctioned, 24 km built. This is not a funding problem — the Centre allocated ₹7,611 crore for Tamil Nadu this year alone — it is a structural execution failure, with land acquisition and project-specific disbursement discipline at the core. The Centre's pattern of announcing large railway allocations for southern states without commensurate delivery has become a persistent electoral grievance, and PMK's intervention signals that the party intends to weaponise it. The proposed monitoring committee is sensible in design, but its value depends entirely on whether the Railway Ministry treats it as a governance tool or a political pacifier.
NationPress
10 Nov 2026

Frequently Asked Questions

What are the 19 pending railway projects in Tamil Nadu that PMK flagged?
The 19 projects comprise eight new railway lines, eight track-doubling works, and three gauge conversion projects, all of which remained incomplete as of 1 April 2026. Their combined estimated cost is ₹27,282 crore, but only ₹8,811 crore — under 33 per cent — has been spent so far.
Why are these Tamil Nadu railway projects delayed?
According to Anbumani Ramadoss's letter, the primary obstacles are inadequate project-specific funding and delays in land acquisition. He also noted that rising construction costs and inflation have absorbed a significant portion of the expenditure already made, leaving physical progress far behind financial outlay.
What has PMK proposed to fix the delays?
PMK has called for a special monitoring committee comprising representatives from the Union Government, the Tamil Nadu government, railway officials, technical experts, and district administrations. The committee would coordinate funding, accelerate land acquisition, and submit monthly progress reports to identify and resolve bottlenecks.
How much has the Centre allocated to Tamil Nadu railways in 2026–27?
The Union Government allocated ₹7,611 crore for Tamil Nadu in the 2026–27 financial year. However, PMK's Anbumani Ramadoss has argued this increased allocation has not translated into meaningful physical progress on the ground.
How much of the new railway line network in Tamil Nadu has actually been completed?
Only 24 kilometres of the planned 811-kilometre new railway line network has been completed, representing approximately 2.95 per cent of the proposed expansion. Cumulative expenditure on these eight new line projects stands at just ₹1,514 crore, under 10 per cent of the ₹15,653 crore estimated cost.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 1 month ago
  2. 4 months ago
  3. 9 months ago
  4. 9 months ago
  5. 9 months ago
  6. 1 year ago
  7. 1 year ago
  8. 1 year ago
Google Prefer NP
On Google