Bullet train trials on Surat-Bilimora route set for May 2027
Synopsis
Key Takeaways
India’s first bullet train project is expected to begin trial runs on the 50-km Surat-Bilimora section in Gujarat in May 2027, Railway Minister Ashwini Vaishnaw said on Monday. The stretch will be the first part of the Mumbai-Ahmedabad High-Speed Rail Corridor to undergo testing.
Vaishnaw said the corridor would be commissioned in phases, with the Ahmedabad-Vapi section targeted for completion by the end of 2027 and services expected to extend to Thane by 2029. He had previously put the target for the first high-speed rail service in the last quarter of 2027.
Surat-Bilimora trial preparations
Electrification of the trial section has been completed, while signalling work is expected to finish by January, according to the minister. The overhead equipment on both the up and down lines of the elevated alignment was energised on 20 November.
The corridor uses a 2x25 kV traction system, which supplies power to trains through overhead equipment. Installation work at the Bilimora traction substation has also been completed, Vaishnaw said.
The trial schedule and the target for passenger operations are separate milestones. Testing the first section would allow its trains and infrastructure to be assessed before the planned start of service; the minister’s stated timeline remains a target rather than a confirmed opening date.
B-28 train and high-speed testing
Initial trials are to use the B-28 train, designed to operate at speeds of up to 280 kmph. Vaishnaw said speeds above 240 kmph fall within the high-speed rail category and require specialised engineering and construction standards.
One challenge described by the minister is managing the pressure generated as trains travel at high speed. Both the rolling stock and the infrastructure must be able to withstand the resulting forces, he said.
Vaishnaw said the B-28 had cleared a squeeze test in which it was subjected to pressure levels twice the atmospheric pressure expected during regular operations. The test assessed the train’s ability to withstand demanding pressure conditions.
Phased corridor rollout
The 508-km corridor links Mumbai and Ahmedabad, two major economic centres, and is intended to reduce travel time between them. The initial 50-km test section is a smaller part of that route, with the broader project scheduled for phased commissioning.
Beyond the first test stretch, Vaishnaw said construction on the Maharashtra portion, including the undersea tunnel, was progressing well. The stated targets place completion of the Ahmedabad-Vapi section at the end of 2027, followed by an extension of services to Thane by 2029.
On 20 November, the minister said the project had moved beyond planning and reiterated the target for a first service in the last quarter of 2027. The next milestones to watch are completion of signalling on the trial section and the planned start of testing in May 2027.