MP power demand jumps 5,000 MW in a year; 3,000-4,000 MW relief due next week
Synopsis
Key Takeaways
Madhya Pradesh is set to receive an additional 3,000 to 4,000 MW of electricity from next week, Energy Minister Pradyuman Singh Tomar said on Thursday, 15 October 2026, as the state grapples with a power crunch triggered by a dramatic surge in demand and reduced generation capacity. The state's peak electricity demand hit 17,124 MW on 14 October 2026, up from 11,874 MW on the same date last year — a jump of roughly 5,000 MW in twelve months.
Where the Extra Power Is Coming From
Generating units at Khandwa and Birsinghpur have already resumed operations following scheduled maintenance, adding around 1,000 MW to available supply. A further 600 MW is expected from Lanco Power and NTPC Gadarwara by 20 October, while units with a combined capacity of approximately 1,200 MW that were shut due to technical faults are expected to come back online within one to two days. An additional 500 MW of banked power is also slated to become available from 16 October.
Tomar noted that despite the shortage, the state supplied 38.6 per cent more electricity on 14 October compared with the same date in 2025 — rising from 2,423 lakh units to 3,310 lakh units.
Why Demand Has Spiked
Agricultural power consumption has been the primary driver of the surge. Demand from the farm sector more than doubled to 3,701 MW on 1 October 2026, up from 1,752 MW on the same date last year. Tomar attributed this to heightened requirements for paddy irrigation and pre-sowing irrigation in areas that received below-normal rainfall this season.
On the supply side, hydropower generation from five major projects — Gandhi Sagar, Omkareshwar, Indira Sagar, Rajghat, and Sardar Sarovar — has fallen by around 1,500 MW due to reduced rainfall. Technical problems at thermal plants have knocked out another 1,000 MW, while coal shortages and unit trippings have further constrained availability.
Power Exchange Near Dry, Prices at ₹10 Per Unit
The nationwide spot market has offered little relief. On 13 October, bids to purchase around 70,000 MW were placed during peak hours on the Indian Energy Exchange (IEX), while sellers offered only approximately 500 MW — with available power priced at ₹10 per unit. The state is currently procuring 500 MW from Uttar Pradesh during peak hours and is attempting to source additional units through the exchange.
For the upcoming rabi season, Madhya Pradesh has arranged advance power banking of around 3,825 million units — 225 million units more than last year's 3,600 million units. This arrangement is expected to provide between 407 MW and 3,900 MW of electricity from 1 November 2026 to 10 March 2027.
Congress Accuses BJP of Poor Preparedness
The power crisis has drawn sharp political fire. State Congress president Jitu Patwari alleged that farmers across several districts were enduring undeclared power cuts and, in some areas, receiving only two to four hours of electricity per day against a government promise of 10 hours.
'Farmers in Madhya Pradesh are waiting for electricity to irrigate their fields. Undeclared power cuts in many districts have left citizens distressed. In some places, farmers' anger is spilling onto the roads, while in others, electricity offices are being locked,' Patwari said.
He demanded a time-bound plan to end unscheduled cuts, immediate procurement of additional power, district-level supply monitoring, and accountability for officials responsible for disruptions. 'Why were no concrete preparations made to ensure electricity availability before the rabi sowing season? The government must immediately ensure 10 hours of power supply to farmers,' he added.
With the rabi sowing window opening and the exchange market stretched, whether the incoming capacity additions will arrive on schedule will determine how severe the disruption to the farm sector becomes over the next fortnight.