Andhra seeks Centre aid for ₹4,851 crore cyclone-proof grid
Synopsis
Key Takeaways
Andhra Pradesh Energy Minister Gottipati Ravikumar has asked the Centre to fund 90 per cent of a ₹4,851 crore plan to make the state's coastal electricity network cyclone-resilient. He raised the request with Union Power Minister Manohar Lal Khattar on Friday, 27 November 2026, on the sidelines of a meeting of state energy ministers in New Delhi. The pitch follows extensive damage to Andhra Pradesh's power infrastructure during the recent cyclones Arnab and Murasu.
Key Developments in New Delhi
The Union Government convened the meeting of energy ministers from various states. Ravikumar used it to hold a separate meeting with Khattar, where he detailed the losses the state's distribution network suffered during the two cyclones.
According to an official release, Ravikumar told the Union Minister that electricity poles, distribution transformers and substations were damaged. The damage disrupted power supply to lakhs of consumers. The release said Khattar responded positively to the proposal.
What the ₹4,851 Crore Proposal Covers
The state government has prepared a comprehensive proposal for vulnerable coastal areas. It has two main parts:
- laying underground cables, and
- rebuilding electricity lines with stronger spun poles.
The estimated cost is ₹4,851 crore. Ravikumar urged the Centre to approve the proposal and provide 90 per cent of the funding. He said the state is prepared to bear the remaining 10 per cent.
The state has drawn up a three-year action plan to complete the works between FY 2027-28 and FY 2029-30. The plan depends on the Centre agreeing to provide financial assistance.
Why Climate-Resilient Power Infrastructure Matters
Ravikumar argued that underground cables and spun poles would significantly reduce damage to electrical infrastructure during cyclones. He said the upgrades would also:
- cut power supply interruptions,
- lower technical losses, and
- allow faster restoration of electricity after natural disasters.
He also made a cost argument. Investing in resilient infrastructure in advance, he said, would be more economical than repeatedly spending large sums on restoring damaged networks after every cyclone.
Andhra Pradesh has one of India's longest coastlines and is regularly exposed to storms from the Bay of Bengal. That makes grid hardening a recurring concern for the state's power utilities and coastal residents.
Telangana's Role in Restoration Efforts
On the sidelines of the meeting, Ravikumar also met Telangana Deputy Chief Minister Bhatti Vikramarka, who represented Telangana at the conclave. Ravikumar thanked him for the help Telangana provided during Cyclones Arnab and Murasu.
He praised the neighbouring state's timely support for restoration work when Andhra Pradesh was facing severe challenges.
What Happens Next
The proposal now awaits formal consideration by the Union Power Ministry. Its approval and the funding share will decide whether work can begin in FY 2027-28 as planned. For coastal consumers who lost power in the recent storms, the outcome will shape how well the grid holds up in future cyclone seasons.