Etthinahole water to reach Tumakuru by November-end, says Karnataka minister

Share:
Audio Loading voice…
Etthinahole water to reach Tumakuru by November-end, says Karnataka minister

Synopsis

After years of delays and a cost escalation from ₹8,000 crore to ₹23,000 crore, the Etthinahole project may finally deliver water to drought-prone Tumakuru by November-end — but the deadline rests on securing a forest clearance from New Delhi within a week and completing a technically challenging 28-metre deep-cut excavation by mid-October.

Key Takeaways

Karnataka Water Resources Minister N.
Cheluvarayaswamy inspected Package 11 works at Kanchiganahalli , Gubbi taluk , on 17 September 2026 .
Water from the Etthinahole project is promised to reach Tumakuru by end of November ; the Tumakuru stretch is targeted for completion by 15 October .
Project cost has escalated from ₹8,000 crore to ₹23,000 crore ; Stage-II forest clearance from the Centre is expected within one week .
A technically demanding 28-metre deep-cut excavation is underway; officials directed to use the cut-and-cover method .
The Bikkegudda project is to be completed and inaugurated within the next two months .
Minister urged farmers to avoid microfinance debt traps and file written complaints to enable government action.

Karnataka Water Resources Minister N. Cheluvarayaswamy on Thursday, 17 September 2026, assured that water from the Etthinahole Integrated Drinking Water Project would be supplied to Tumakuru by the end of November, following a site inspection of ongoing works under Package 11 of the project at Kanchiganahalli in Gubbi taluk. The minister directed officials to accelerate construction and underscored the government's commitment to ensuring 100 per cent of the planned water supply.

About the Etthinahole Project

The Yettinahole Integrated Drinking Water Project is a flagship water-supply initiative in Karnataka, designed to divert water from the Yettinahole stream — a tributary of the Netravati river — to drought-prone districts across eastern and central Karnataka, including Tumakuru. Originally estimated at ₹8,000 crore, the project's cost has since escalated to ₹23,000 crore, reflecting the scale and complexity of the civil works involved. Minister Cheluvarayaswamy described it as a 'dream project' first launched during the previous Congress government.

Key Developments on the Ground

During his inspection at Kanchiganahalli, the minister reviewed a 1.9-km stretch of construction on land belonging to the Forest Department. He stated that work on the Tumakuru stretch is targeted for completion by 15 October, ahead of the overall November-end supply deadline. He also confirmed that files related to the Stage-II forest clearance required for the project have already reached New Delhi, with the Additional Chief Secretary of the Forest Department having submitted the application. Cheluvarayaswamy expressed confidence that the final clearance from the Centre would be secured within a week.

Construction Challenges and Directives

The minister highlighted a technically demanding phase of the project: an excavation requiring a deep cut of 28 metres at the site. He directed officials to adopt the cut-and-cover method to prevent soil collapse and ensure that construction meets required quality and safety standards. He also instructed that an additional 10 acres of land allotted for temporary soil storage be used effectively, with excavated soil refilled properly upon completion. Officials were told to give the highest priority to quality in the construction of the gravity canal.

Other Announcements and Farmer Concerns

Cheluvarayaswamy also announced that the Bikkegudda project, delayed due to what he described as unavoidable reasons, would be completed and inaugurated within the next two months. On the contentious Hemavathi Link Canal project, which some farmers have demanded be scrapped, the minister advocated a balanced approach. 'Farmers in both Tumakuru and Ramanagara are equal to us. Everyone is our own. We will hold detailed discussions with the Chief Minister and take appropriate measures that are in the interest of everyone without causing injustice to anyone,' he said. The minister additionally raised concerns about financial exploitation of farmers through microfinance institutions, urging them to avoid the debt trap and file written complaints if they face harassment, noting that legal action requires formal written grievances. Gubbi MLA and KSRTC Corporation Chairman P. Vasu along with Water Resources Department officials were present at the inspection.

What Happens Next

The project's immediate milestones hinge on securing Stage-II forest clearance from the Centre and completing the Tumakuru stretch by mid-October. If the timeline holds, residents of water-stressed Tumakuru districts could receive Etthinahole supply before the year ends — a development that would mark a significant milestone for a project years in the making.

Point of View

But the deadline is tightly contingent on two variables the state does not fully control: a forest clearance from the Centre and flawless execution of a 28-metre deep excavation. The project's cost nearly tripling — from ₹8,000 crore to ₹23,000 crore — is a red flag that deserves scrutiny beyond the ministerial reassurance. Karnataka has a history of water-project timelines slipping, and with elections never far from the political calendar, the November-end pledge carries as much electoral weight as engineering ambition.
NationPress
17 Sept 2026

Frequently Asked Questions

What is the Etthinahole (Yettinahole) project in Karnataka?
The Yettinahole Integrated Drinking Water Project is a large infrastructure initiative that diverts water from the Yettinahole stream, a tributary of the Netravati river, to drought-prone eastern and central Karnataka districts, including Tumakuru. Originally estimated at ₹8,000 crore, its cost has now risen to ₹23,000 crore.
When will Tumakuru receive water from the Etthinahole project?
Karnataka Water Resources Minister N. Cheluvarayaswamy has promised water supply to Tumakuru by end of November 2026. The Tumakuru construction stretch is targeted for completion by 15 October, ahead of that supply deadline.
What is the status of the forest clearance needed for the project?
Stage-II forest clearance files for the Etthinahole project have already been submitted in New Delhi by the Additional Chief Secretary of the Forest Department. The minister expressed confidence that final clearance from the Centre would be obtained within one week.
Why has the Etthinahole project's cost increased so sharply?
The project's estimated cost has escalated from approximately ₹8,000 crore to ₹23,000 crore, nearly tripling. The minister acknowledged the increase but did not detail specific reasons, stating that the government remains committed to completing the project in the interest of farmers.
What other projects did the minister announce during the inspection?
Minister Cheluvarayaswamy announced that the Bikkegudda project, which had been delayed, would be completed and inaugurated within two months. He also said the government would take a balanced approach on the Hemavathi Link Canal project following demands from farmers to drop it.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 1 month ago
  2. 1 month ago
  3. 2 months ago
  4. 2 months ago
  5. 4 months ago
  6. 11 months ago
  7. 1 year ago
  8. 1 year ago
Google Prefer NP
On Google