Shillong Peak ropeway: ₹151 crore project targets October 2028 completion

Share:
Audio Loading voice…
Shillong Peak ropeway: ₹151 crore project targets October 2028 completion

Synopsis

Meghalaya has laid out detailed plans for a ₹151 crore ropeway at Shillong Peak — a project decades in the making, blocked by Defence-land access restrictions and steep terrain. Funded jointly by the New Development Bank and PM-DevINE, the 913-metre link targets a 2028 finish and promises 450+ jobs, but community deliberations are still ongoing.

Key Takeaways

Meghalaya's ₹151 crore Shillong Peak ropeway is targeted for completion by 14 October 2028 .
The project spans 913 metres and will operate 11 passenger cabins plus two additional cabins, implemented by the MRDA .
Funding comes from ₹80.89 crore (NDB) and ₹70.11 crore (PM-DevINE) .
The upper terminal is sited 80 metres below the viewpoint to address Air Force security concerns.
An Environmental Impact Study found no significant impact on catchment areas; tree cutting limited to six tower sites .
The project is projected to generate more than 450 direct and indirect jobs across tourism, hospitality, transport and retail.

Meghalaya's ₹151 crore Shillong Peak ropeway project is on course for completion by 14 October 2028, with the government presenting its design, environmental safeguards and community engagement plan at a briefing in Shillong on Friday, 23 October 2026. The project is expected to ease long-standing access difficulties at one of the state's most visited viewpoints while generating more than 450 direct and indirect jobs.

Project Design and Scale

The ropeway, being implemented by the Meghalaya Ropeway Development Authority (MRDA), will span 913 metres and operate 11 passenger cabins along with two additional cabins. The upper terminal is proposed at a point roughly 80 metres below the Shillong Peak viewpoint — a deliberate design choice to preserve panoramic sightlines and address Indian Air Force security concerns over the Defence-controlled land that visitors have historically had to cross to reach the peak.

The lower terminal is planned at a government forest nursery in Madan Laban, which officials assessed as having no impact on water catchment areas in the vicinity.

Funding and Background

The project draws on two funding streams: ₹80.89 crore from the New Development Bank (NDB) and ₹70.11 crore under the Prime Minister's Development Initiative for North Eastern Region (PM-DevINE), routed through the Ministry of Development of North Eastern Region. Efforts to improve access at Shillong Peak date to 2012, when footpaths from Madan Laban and Upper Lumparing were developed. The steep terrain limited their usability, prompting the government to begin exploring a ropeway solution in 2019.

Environmental Safeguards

Officials sought to address concerns about forest cover, water sources and the broader landscape, stating that the ropeway alignment follows a ridge and that an Environmental Impact Study — conducted in line with NDB requirements — identified no significant impacts on catchment areas. The towers will be situated outside the Umiew catchment and Mawphlang Dam area, according to the government presentation. Cables and cabins are designed to operate above the tree canopy, with tree cutting restricted to six tower locations and the two terminal stations. The sacred site of Lum Shyllong is located 3.15 km from the proposed alignment, officials noted. Reduced vehicular traffic to the viewpoint is also expected to ease congestion and cut emissions.

Community Response and Consultations

The briefing at the State Convention Centre was co-chaired by the MRDA chief executive officer and the Tourism Department's Commissioner and Secretary. Consultations and site inspections have been conducted with local stakeholders, including the Riat Laban Dorbar Pyllun. Community representatives reportedly welcomed the clarifications but said they required more time to examine the details before deliberating further. The government urged stakeholders to cooperate, highlighting the project's potential for tourism infrastructure and local livelihoods.

Economic and Tourism Impact

Beyond easing access, the project is projected to create more than 450 direct and indirect employment opportunities across tourism, hospitality, transport and retail. With Meghalaya pushing to expand its tourism footprint in the Northeast, the Shillong Peak ropeway is positioned as a flagship infrastructure investment that could also reduce the overcrowding and road stress that currently mark peak visitor seasons. Whether the October 2028 deadline holds will depend on statutory clearances, stakeholder consensus and on-ground execution — all of which remain works in progress.

Point of View

And the access problem it addresses dates to 2012 — a timeline that underscores how slowly infrastructure moves in terrain-challenged, Defence-adjacent zones in the Northeast. The dual-funding structure (NDB plus PM-DevINE) insulates the project from single-source budget risk, but the community response — welcoming yet non-committal — signals that stakeholder consensus is not yet secured. With statutory clearances still pending and a 2028 deadline in view, the real test is whether MRDA can compress decision-making without alienating the local dorbar bodies whose buy-in is essential for smooth construction.
NationPress
23 Oct 2026

Frequently Asked Questions

What is the Shillong Peak ropeway project?
The Shillong Peak ropeway is a ₹151 crore infrastructure project in Meghalaya that will connect Madan Laban to a point near the Shillong Peak viewpoint via a 913-metre ropeway with 11 passenger cabins. It is being implemented by the Meghalaya Ropeway Development Authority and is targeted for completion by 14 October 2028.
How is the Shillong Peak ropeway being funded?
The project is jointly funded by ₹80.89 crore from the New Development Bank (NDB) and ₹70.11 crore under the Prime Minister's Development Initiative for North Eastern Region (PM-DevINE), channelled through the Ministry of Development of North Eastern Region.
Why is a ropeway needed at Shillong Peak?
Visitors to Shillong Peak have long depended on routes passing through Defence-controlled land, which is subject to security restrictions. Footpath alternatives developed from 2012 were impractical due to steep terrain, prompting the government to explore a ropeway solution from 2019 onwards.
What are the environmental safeguards for the project?
An Environmental Impact Study conducted in accordance with NDB requirements found no significant impacts on water catchment areas. Towers will be outside the Umiew catchment and Mawphlang Dam zone, cables and cabins will operate above the tree canopy, and tree cutting will be confined to six tower locations and the two terminal stations.
How many jobs will the Shillong Peak ropeway create?
The project is expected to generate more than 450 direct and indirect employment opportunities across tourism, hospitality, transport and retail sectors in the region.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 3 months ago
  2. 4 months ago
  3. 4 months ago
  4. 5 months ago
  5. 1 year ago
  6. 1 year ago
  7. 1 year ago
  8. 1 year ago
Google Prefer NP
On Google