Karnataka to fast-track UKP Stage-3 land acquisition, ₹3,000 crore compensation for 184 villages

Share:
Audio Loading voice…
Karnataka to fast-track UKP Stage-3 land acquisition, ₹3,000 crore compensation for 184 villages

Synopsis

Karnataka has put a ₹3,000 crore compensation framework on the table for 184 villages facing submergence under UKP Stage-3 — and sharply revised rates from ₹2 lakh to up to ₹40 lakh per acre signal how politically charged this water project has become. With 71,284 acres still pending acquisition and Lok Adalats clearing court backlogs, the real test is whether disbursal matches the deadline.

Key Takeaways

Water Resources Minister N.
Cheluvarayaswamy directed officials on 21 September 2026 to expedite UKP land acquisition and compensation at Vidhana Soudha, Bengaluru .
184 villages face submergence from Almatti reservoir backwaters; acquisition is already at various stages in 79 villages .
Compensation target for this year: 15,000 acres out of a total 75,563 acres ; ₹3,000 crore to be split equally among six Assembly constituencies .
Compensation rates revised from ₹2 lakh per acre to ₹40 lakh per acre (irrigated) and ₹30 lakh per acre (dry land) last year.
UKP Stage-3 requires 1,33,867 acres ; raising Almatti dam gates from 519.60 m to 524.256 m will add 100 TMC of storage.
Acquisition completed in 18 villages ; 71,284 acres across 166 villages remain pending; court cases being settled via Lok Adalats .

Karnataka Water Resources Minister N. Cheluvarayaswamy on Monday, 21 September 2026 directed officials to accelerate pending compensation payouts under the first two phases of the Upper Krishna Project (UKP) and simultaneously begin land acquisition for UKP Stage-3 on a proportionate basis as prescribed under government rules. The directives were issued at a high-level meeting held at Vidhana Soudha, Bengaluru, focused on the acquisition of land across 184 villages expected to be submerged by the backwaters of the Almatti reservoir.

Key Directions from the Meeting

Cheluvarayaswamy instructed officials to strictly follow government guidelines and avoid arbitrary decisions during the acquisition process. Ministers and legislators from constituencies falling under the project area have been permitted to submit written suggestions on the various stages of acquisition. The minister clarified that compensation rates per acre were fixed under an order issued last year, and officials unclear about building compensation should formally write to the department for guidance. He added that the matter would be escalated to the Chief Minister for appropriate directives.

Gram panchayats have been entrusted with identifying land for rehabilitation purposes. Cheluvarayaswamy also warned of legal action over reported allegations involving sale agreements at rehabilitation centres for amounts running into crores of rupees. A separate meeting on rehabilitation centre shelters is to be convened shortly to safeguard the interests of project-affected families.

Phased Acquisition Plan: 184 Villages in Focus

Officials held detailed discussions on prioritising 79 villages where land acquisition is already at various stages. The government will take up acquisition of another 87 villages — for which notifications are yet to be issued — based on flood-affected status, while villages in the final stage will be considered later. The government has set a target of distributing compensation for approximately 15,000 acres out of a total 75,563 acres this year.

Minister M.B. Patil urged that for the 5,600 acres in Babaleshwar, compensation for at least 1,000 acres should be provided immediately. He noted that although funds had been released for 18 villages, those in Vijayapura district were excluded. In response, Cheluvarayaswamy assured that the proposed ₹3,000 crore would be distributed equally among the six Assembly constituencies covered by the project, with ₹500 crore allocated to each.

What UKP Stage-3 Entails

UKP Stage-3 envisages raising the height of Almatti dam gates from 519.60 metres to 524.256 metres, which would enable storage of an additional 100 TMC of water and the implementation of nine sub-projects. The project requires acquisition of 1,33,867 acres of land in total. Notably, compensation rates — earlier fixed at ₹2 lakh per acre — were sharply revised last year to ₹40 lakh per acre for irrigated land and ₹30 lakh per acre for dry land, a significant increase aimed at addressing long-standing grievances of affected farmers.

Land acquisition has already been completed in 18 villages, while acquisition remains pending for 71,284 acres across 166 villages. Some pending court cases are being resolved through Lok Adalats.

Other Officials and Additional Issues

The meeting was attended by ministers Vijanand Kashappanavar and Laxman Savadi, former minister R.B. Thimmapur, Water Resources Department Additional Chief Secretary Gaurav Gupta, and senior officials of Krishna Bhagya Jala Nigam Limited (KBJNL).

In a separate meeting later on the same day, Cheluvarayaswamy addressed land acquisition concerns in Govindapalli and Karadigudda villages in Devadurga taluk, which are affected by the backwaters of Ramadurga tank. He assured farmers that compensation steps would be initiated, directing officials to study the affected area and submit a report covering 243.43 acres of land.

With compensation rates overhauled and a structured timeline now in place, the pace of UKP-3 implementation over the coming months will be closely watched by tens of thousands of project-affected families across six constituencies.

Point of View

000 crore outlay across just six constituencies. The decision to use gram panchayats for rehabilitation land identification is participatory on paper, but without clear accountability, it could become another layer of delay. The Lok Adalat route for court cases is pragmatic, yet the fact that 166 villages remain unacquired years into the project underscores a structural gap between irrigation ambition and ground-level execution in Karnataka. Whether the ₹500 crore per constituency formula will hold — or buckle under competing local pressures — will define UKP-3's credibility.
NationPress
22 Sept 2026

Frequently Asked Questions

What is the Upper Krishna Project Stage-3 and why is it significant?
UKP Stage-3 involves raising the Almatti dam gate height from 519.60 metres to 524.256 metres, enabling storage of an additional 100 TMC of water alongside nine sub-projects, requiring acquisition of 1,33,867 acres of land. It is one of Karnataka's largest ongoing irrigation undertakings, directly affecting hundreds of villages across multiple districts.
How much compensation will affected farmers receive under UKP Stage-3?
Compensation rates were revised last year from ₹2 lakh per acre to ₹40 lakh per acre for irrigated land and ₹30 lakh per acre for dry land. The government has proposed distributing ₹3,000 crore equally among six Assembly constituencies, with ₹500 crore allocated to each.
How many villages are affected and what is the acquisition status?
A total of 184 villages face submergence from Almatti reservoir backwaters. Acquisition is completed in 18 villages, at various stages in 79 villages, and pending for 71,284 acres across 166 villages. Notifications are yet to be issued for another 87 villages.
What is the government's compensation target for the current year?
The Karnataka government has set a target of distributing compensation for around 15,000 acres out of the total 75,563 acres this year. Minister M.B. Patil specifically urged that compensation for at least 1,000 acres in Babaleshwar be provided immediately.
How are pending legal disputes over UKP land acquisition being resolved?
Court cases related to UKP land acquisition are being resolved through Lok Adalats, offering an out-of-court settlement mechanism for affected families. The government has also warned of legal action over alleged sale agreements involving rehabilitation centres for amounts running into crores of rupees.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 1 month ago
  2. 2 months ago
  3. 6 months ago
  4. 6 months ago
  5. 6 months ago
  6. 9 months ago
  7. 1 year ago
  8. 1 year ago
Google Prefer NP
On Google