Infra cost overrun hits ₹3.28 lakh crore in October: MoSPI data
Synopsis
Key Takeaways
India's large infrastructure projects recorded a cumulative cost overrun of ₹3.28 lakh crore in October 2026, pushing their revised total cost to ₹38.11 lakh crore, according to data released by the Ministry of Statistics and Programme Implementation (MoSPI) in New Delhi on Thursday, 26 November 2026. The figures cover Central projects worth more than ₹150 crore each across 17 Central ministries and departments.
The release comes as the Finance Ministry asks ministries to explain cost escalations on capital projects before it allocates more funds.
Key Numbers from the MoSPI Report
Total expenditure on these projects has reached ₹17.87 lakh crore, about 46.88 per cent of the revised project cost. MoSPI said this indicates steady progress in implementation.
A large share of the portfolio is at advanced stages. 649 projects (35 per cent) have crossed 80 per cent physical progress, while 326 projects (18 per cent) have crossed 80 per cent financial completion.
The ministry described the pipeline as balanced, with projects spread across early and advanced stages of implementation.
Sector-wise Breakdown
The transport and logistics sector has the largest number of ongoing projects, with 1,324 projects carrying a cumulative cost of ₹20.37 lakh crore. That is more than half of the total revised cost. The report said this reflects the priority given to connectivity-led infrastructure.
The Ministry of Railways has 288 ongoing projects (15 per cent) with a revised cost of ₹7.38 lakh crore (19 per cent). The Coal Ministry accounts for 121 projects (7 per cent) worth ₹2.22 lakh crore (6 per cent).
Other ministries and departments are implementing the following:
- Ministry of Petroleum and Natural Gas: 117 projects worth ₹4.42 lakh crore
- Ministry of Power: 108 projects worth ₹6.55 lakh crore
- Ministry of Housing and Urban Affairs: 50 projects worth ₹3.44 lakh crore
- Department of Water Resources, River Development & GR: 33 projects worth ₹1.93 lakh crore
The remaining 173 projects (9 per cent), worth ₹2.63 lakh crore (7 per cent), are spread across several ministries and departments. These include Higher Education, Civil Aviation, Steel, Telecommunications, Labour and Employment, Ports, Shipping and Waterways, Health and Family Welfare, Mines, DPIIT, and Sports.
How Physical and Financial Progress Compare
According to the report, physical and financial progress broadly move together. Many projects are clustered at the initial stage (0-20 per cent) and the advanced stage (81-100 per cent), which points to a mix of newly started projects and projects nearing completion.
The two measures diverge at either end of the cycle:
- Early stages: financial progress runs relatively higher than physical progress, which MoSPI attributes to upfront spending.
- 81-100 per cent range: physical progress runs ahead of financial progress.
Finance Ministry Tightens Scrutiny
The Finance Ministry is seeking detailed explanations from ministries for cost escalations that exceed the tolerance limit by 10 per cent on capital and infrastructure projects above ₹5 crore. Ministries must state whether the overruns come from implementation delays, higher input costs or other factors. They must also submit revised timelines before additional funds are released.
The coming months will test whether this tighter review curbs cost escalation across India's ₹38 lakh crore project pipeline.