Centre monitors 1,862 infra projects worth ₹38.11 lakh crore

Share:
Audio Loading voice…
Centre monitors 1,862 infra projects worth ₹38.11 lakh crore

Synopsis

Nearly half of India's ₹38.11 lakh crore central infrastructure pipeline is already spent, with 1,862 projects on MoSPI's PAIMANA-PROJ dashboard. Transport dominates the count, water leads on spend ratio, and 649 projects have crossed 80 per cent physical progress.

Key Takeaways

The Centre is monitoring 1,862 central sector infrastructure projects worth ₹38.11 lakh crore as of 25 November 2026 .
Nearly ₹17.87 lakh crore , or about 46.9 per cent , has already been spent.
649 projects ( 35 per cent ) have crossed 80 per cent physical progress; 326 have crossed 80 per cent financial completion.
Transport and logistics account for 1,324 projects worth ₹20.37 lakh crore — more than 70 per cent of the monitored set.
Roads and highways: 972 projects worth ₹9.55 lakh crore ; railways: 288 projects worth ₹7.38 lakh crore ; energy: 229 projects worth ₹11.31 lakh crore .
The next monthly status report for November 2026 is due on 28 December .

The Centre is currently monitoring 1,862 central sector infrastructure projects with a combined cost of ₹38.11 lakh crore, of which nearly ₹17.87 lakh crore — about 46.9 per cent — has already been spent, the Ministry of Statistics and Programme Implementation (MoSPI) said in New Delhi on Wednesday, 25 November 2026. The works are being tracked on MoSPI's PAIMANA-PROJ platform, which covers infrastructure projects costing ₹150 crore and above across 17 ministries and departments.

Physical and financial progress

649 projects, or about 35 per cent of the monitored set, have achieved more than 80 per cent physical progress, while 326 projects have crossed the 80 per cent financial completion mark, indicating that a significant number of projects are nearing completion, according to the official statement.

The gap between the two milestones is notable: far more packages have crossed the 80 per cent physical threshold than the financial one. Officials did not separately explain the lag, but the figures suggest that a large share of the ₹38.11 lakh crore pipeline still sits in the unspent half even as on-ground work on hundreds of sites is in the final stretch.

Transport dominates the pipeline

The transport and logistics sector remains the largest component of the infrastructure pipeline, accounting for 1,324 projects worth ₹20.37 lakh crore and representing more than 70 per cent of all monitored projects. Roads and highways alone account for 972 projects valued at ₹9.55 lakh crore, followed by 288 railway projects worth ₹7.38 lakh crore.

This comes amid a sustained Centre push to expand highway and rail capacity. Notably, roads and highways make up more than half of the 1,862-project count even though their combined cost is lower than the energy sector's outlay — a pattern of many highway packages versus fewer, more capital-intensive power and transmission works.

Energy, water and sanitation

The energy sector comprises 229 projects with a combined cost of ₹11.31 lakh crore. Water and sanitation projects worth ₹1.97 lakh crore have recorded the highest expenditure-to-cost ratio at nearly 70 per cent — well above the overall 46.9 per cent spend rate for the full monitored set.

That contrast matters for execution tracking. Water and sanitation appears furthest along in rupee terms, while energy, despite a much larger ticket size, still carries a substantial unspent balance if the overall average is any guide. MoSPI did not publish a sector-wise spend percentage for energy in this update.

October commissions and new additions

During October, several notable projects were commissioned, including the ₹4,445-crore renewable energy transmission scheme in Karnataka, the ₹641-crore six-lane elevated corridor on NH-66, and the ₹884-crore Coke Oven Battery rebuild project at Bhilai Steel Plant.

The government also onboarded 38 new projects onto the monitoring platform during the month. Key additions include the ₹4,464-crore access-controlled highway connecting Vadhavan Port and NH-48, the ₹3,842-crore NH-752D road project in Madhya Pradesh, and two phases of the Ahmedabad Metro Rail Project valued at more than ₹3,200 crore combined.

Digital tracking and the next update

MoSPI said the monitoring framework is increasingly supported by digital integration, with nearly 80 per cent of project data now being updated through APIs, helping strengthen real-time infrastructure tracking and data-driven decision-making across ministries. The government also announced that the next monthly infrastructure status report for November 2026 is scheduled to be released on 28 December.

Agencies watching the pipeline will look to that December release for whether the 46.9 per cent spend ratio and the 80-per-cent-progress cohort continue to rise as the newly onboarded highway and metro packages enter the dashboard.

Point of View

With 35 per cent of projects past 80 per cent physical progress, shows a pipeline that is mid-to-late cycle on many packages yet still carrying a large unspent balance. Transport's 70-plus per cent share of the count, versus energy's outsized rupee weight, is the structural story: India is still building roads by the hundred while a smaller set of power projects absorbs capital. The 80 per cent API feed is the under-reported shift — if ministries actually update in real time, delays become harder to hide, and the 28 December print will show whether newly onboarded Vadhavan, NH-752D and Ahmedabad Metro packages dilute the spend ratio before they start to lift it.
NationPress
25 Nov 2026

Frequently Asked Questions

What is the ₹38.11 lakh crore infrastructure monitoring update?
The Centre is monitoring 1,862 central sector infrastructure projects costing ₹38.11 lakh crore through MoSPI's PAIMANA-PROJ platform, which covers works of ₹150 crore and above across 17 ministries. About ₹17.87 lakh crore, or 46.9 per cent of the combined cost, has already been spent.
How many infrastructure projects have crossed 80 per cent progress?
649 projects, or about 35 per cent of the monitored pipeline, have achieved more than 80 per cent physical progress, while 326 projects have crossed the 80 per cent financial completion mark. MoSPI said this indicates a significant number of projects are nearing completion.
Which sector dominates India's monitored infrastructure pipeline?
Transport and logistics is the largest component, with 1,324 projects worth ₹20.37 lakh crore — more than 70 per cent of all monitored projects. Roads and highways account for 972 projects valued at ₹9.55 lakh crore, followed by 288 railway projects worth ₹7.38 lakh crore.
Which projects were commissioned or added in October?
Commissioned works included a ₹4,445-crore renewable energy transmission scheme in Karnataka, a ₹641-crore six-lane elevated corridor on NH-66, and an ₹884-crore Coke Oven Battery rebuild at Bhilai Steel Plant. The government also onboarded 38 new projects, including a ₹4,464-crore highway linking Vadhavan Port and NH-48, a ₹3,842-crore NH-752D road in Madhya Pradesh, and two Ahmedabad Metro phases worth more than ₹3,200 crore combined.
When will the next MoSPI infrastructure status report be released?
The next monthly infrastructure status report, covering November 2026, is scheduled to be released on 28 December. Nearly 80 per cent of project data on PAIMANA-PROJ is now updated through APIs.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 1 month ago
  2. 2 months ago
  3. 3 months ago
  4. 3 months ago
  5. 5 months ago
  6. 6 months ago
  7. 7 months ago
  8. 8 months ago
Google Prefer NP
On Google