Assam Assembly complex in Dibrugarh to be ready in 30 months: CM Sarma
Synopsis
Key Takeaways
Assam Chief Minister Himanta Biswa Sarma on Wednesday, 14 October 2026, inspected the ongoing construction of the Assam Legislative Assembly complex at Khanikar in Dibrugarh, reaffirming a 30-month deadline for project completion. The complex is a centrepiece of the state government's ambition to develop Dibrugarh as Assam's second capital.
Project Status and Scale
Spread across approximately 63 bighas of land, the complex is still in its early stages. Officials informed Sarma that around 20 per cent of the piling work has been completed and that construction of the boundary wall is progressing. The Chief Minister discussed weather-related challenges with executing agencies and reportedly suggested modifications to the building's front elevation and overall architectural design.
According to the approved master plan, the complex will include a three-storey Assembly building, a nine-storey MLA hostel above the ground floor, an auditorium, a secretariat block, and barracks. Internal roads, parking facilities, and landscaped green spaces are also part of the blueprint.
What the Chief Minister Said
'The construction of the Assam Legislative Assembly complex in Dibrugarh is an important step towards developing the city as the state's second capital,' Sarma said during the inspection, reiterating the 30-month completion target. The proposed infrastructure is designed to accommodate full legislative proceedings and support facilities for legislators and officials as Dibrugarh transitions into a secondary administrative hub.
Sports Complex Concerns Flagged
Later in the day, Sarma also inspected the Multi-Disciplinary Sports Complex at Khanikar and reviewed concerns relating to infrastructure quality and safety. Journalists accompanying the Chief Minister flagged issues including steep and narrow steps in the spectator galleries, sanitary fitting deficiencies, inadequate swimming pool temperature control, poor lighting, water-level management problems, and leakage from the indoor stadium's roof.
Sarma directed the officials concerned and contractors to address the reported deficiencies and undertake corrective measures. The stadium currently holds approximately 5,000 spectators, with a proposal to expand its capacity to around 35,000.
Bigger Picture: Dibrugarh as Second Capital
The twin inspections signal the state government's accelerating push to build Dibrugarh's administrative and public infrastructure from the ground up. This comes amid broader efforts under the Sarma administration to decentralise governance eastward, reducing dependence on Guwahati as the sole seat of state power. If the 30-month timeline holds, the Assembly complex could be operational by early 2029, potentially hosting legislative sessions outside Guwahati for the first time in the state's history.