DMRC begins Shivaji Stadium Metro construction under Central Vista Corridor

Share:
Audio Loading voice…
DMRC begins Shivaji Stadium Metro construction under Central Vista Corridor

Synopsis

Delhi Metro's most complex underground challenge yet: the new Shivaji Stadium station must be built 38 metres deep — 12 storeys below the surface — directly beneath the existing Airport Express Line. With construction now live at a second Central Vista Corridor station, Delhi's most ambitious Metro expansion in years is firmly underway.

Key Takeaways

DMRC commenced construction at Shivaji Stadium Metro Station on 25 August 2026 under the Central Vista Corridor .
The station is part of the Magenta Line Phase V(A) extension from Janakpuri West to R.K.
A 230-metre subway will integrate the new station with the existing Airport Express Line ; an 800-metre subway with travelators will connect it to Rajiv Chowk .
The diaphragm wall will be 38 metres deep — equivalent to a 12-storey building — due to construction below the Airport Express Line.
The Central Vista Corridor spans 9.913 km with nine underground stations ; Central Secretariat station construction began on 24 June 2026 .
Monthly construction activity will generate approximately 750 dumper trips and 500 transit mixer trips .

The Delhi Metro Rail Corporation (DMRC) on Tuesday, 25 August commenced construction at the Shivaji Stadium Metro Station, marking a significant step in the Central Vista Corridor project — a 9.913-km underground stretch that will add nine new stations to Delhi's Metro network. Lieutenant Governor T.S. Sandhu described the commencement as a 'major milestone for the Delhi Metro.'

What the Station Will Offer

The Shivaji Stadium station is being built under Phase V(A) as an extension of the existing Magenta Line from Janakpuri West to R.K. Ashram Marg. Once operational, it is expected to serve office workers in the surrounding area, school students, devotees visiting Bangla Sahib Gurudwara, and passengers connecting to the Airport Express Line.

Critically, the new underground station will be integrated with the existing Shivaji Stadium Airport Express Line station via a 230-metre-long subway, enabling seamless interchange between the two corridors. A separate 800-metre-long subway — fitted with travelators — will link the station to Rajiv Chowk Metro Station, improving pedestrian connectivity across a key central Delhi junction.

Engineering Scale and Construction Complexity

The station's diaphragm wall will reach approximately 38 metres below ground — equivalent to the height of a 12-storey building — because the new station must be built beneath the existing Airport Express Line alignment. This depth makes it one of the more technically demanding excavations in the Delhi Metro's construction history.

The construction logistics are equally significant. According to the DMRC statement, pouring around 3,000 cubic metres of concrete per month will require approximately 500 transit mixer trips, while excavating nearly 15,000 cubic metres per month will generate about 750 dumper trips monthly — or roughly 25 dumper trips per day — to remove excavated material. Commuters and residents in the area should expect notable construction vehicle movement as work progresses.

The Nine-Station Central Vista Corridor

The Central Vista Corridor will comprise nine underground stations: Shivaji Stadium, Yuge Yugeen Bharat, Central Secretariat, Kartavya Bhawan, India Gate, War Memorial–High Court, Baroda House, Bharat Mandapam, and Indraprastha. Construction at Central Secretariat Metro Station under the same corridor had already begun on 24 June 2026, making Shivaji Stadium the second station on the corridor to enter active construction.

Connectivity and Strategic Significance

The corridor is designed to strengthen Metro access to key government offices, judicial institutions, national memorials, and convention facilities in central New Delhi. Lieutenant Governor Sandhu said the administration remains 'fully committed to providing all necessary support and cooperation to ensure its continued progress and expansion.' With two of the nine stations now under construction, the Central Vista Corridor is transitioning from planning to active execution — a phase that will test both engineering timelines and traffic management in one of Delhi's most congested zones.

Point of View

And the sequencing of construction starts — Central Secretariat in June, Shivaji Stadium in August — suggests DMRC is managing site complexity rather than optics. The 38-metre diaphragm wall beneath a live Airport Express Line is a genuine engineering challenge, not a routine dig. What the announcement leaves unanswered is the completion timeline: with nine stations, significant excavation volumes, and central Delhi traffic constraints, the project's delivery window will determine whether it becomes a legacy asset or a prolonged disruption. The absence of a commissioning date in official communications is notable.
NationPress
25 Aug 2026

Frequently Asked Questions

What is the Central Vista Corridor Metro project?
The Central Vista Corridor is a 9.913-km underground Delhi Metro stretch comprising nine new stations, including Shivaji Stadium, Central Secretariat, India Gate, and Indraprastha. It is being built under Phase V(A) as an extension of the Magenta Line from Janakpuri West to R.K. Ashram Marg.
Why is the Shivaji Stadium Metro station being built so deep?
The station's diaphragm wall will go approximately 38 metres underground — equivalent to a 12-storey building — because it must be constructed below the existing Airport Express Line alignment. This makes it one of the more technically complex stations in Delhi Metro's construction history.
How will Shivaji Stadium Metro station connect to other lines?
The new station will be linked to the existing Shivaji Stadium Airport Express Line station via a 230-metre subway, enabling interchange between the Magenta Line and Airport Express corridors. A separate 800-metre subway with travelators will also connect it to Rajiv Chowk Metro Station.
Which other Central Vista Corridor stations are under construction?
Construction at Central Secretariat Metro Station under the same corridor began on 24 June 2026, making it the first station to break ground. Shivaji Stadium, which commenced on 25 August 2026, is the second. Seven more stations are yet to begin active construction.
Who will benefit from the Shivaji Stadium Metro station?
The station is expected to serve office employees in the surrounding area, school students, devotees visiting Bangla Sahib Gurudwara, and passengers connecting between the Magenta Line and the Airport Express Line. It will also improve pedestrian connectivity to Rajiv Chowk.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 1 month ago
  2. 1 month ago
  3. 1 month ago
  4. 2 months ago
  5. 3 months ago
  6. 5 months ago
  7. 1 year ago
  8. 1 year ago
Google Prefer NP
On Google