Green energy projects get 4-month extension amid West Asia crisis delays
Synopsis
Key Takeaways
The Ministry of New and Renewable Energy (MNRE) on 21 August 2026 issued an advisory directing state governments and power sector public sector undertakings (PSUs) to grant up to four months' extension to renewable energy projects whose timelines have been disrupted by the ongoing West Asia crisis, invoking Force Majeure provisions under existing power purchase agreements. The relief covers projects whose scheduled supply or commissioning dates fall on or after 28 February 2026.
The Legal Basis for the Extension
The advisory draws its authority from an order dated 29 April 2026 issued by the Department of Expenditure, Ministry of Finance, which officially classified the West Asia situation as equivalent to 'war' for the purposes of Force Majeure clauses in contracts. Most Power Purchase Agreements (PPAs) already include 'war' as a recognised Force Majeure event, making this classification the critical enabling step for project developers to seek relief without renegotiating individual contracts.
The extension applies to both the Scheduled Commencement of Supply Date (SCSD) and the Scheduled Commissioning Date (SCD), covering the full spectrum of project milestones where delays can attract penalties or trigger contract breaches.
Who Can Grant the Extension
Renewable Energy Implementing Agencies (REIAs) — including the Solar Energy Corporation of India (SECI), NTPC, NHPC, and SJVN — are authorised to process and approve extension requests from affected developers. Power, energy, and renewable energy departments of state and union territory governments are similarly empowered. Agencies are required to follow the contractual procedure specified in the relevant PPA while processing each request.
Why the Advisory Was Issued
MNRE received multiple representations from renewable power developers citing supply chain disruptions and logistical delays linked to the West Asia conflict. Developers had also pointed to a separate advisory issued by the Ministry of Housing and Urban Affairs (MoHUA) on 31 July 2026 to real estate regulatory authorities, which provided a comparable four-month extension for registered real estate projects. Developers argued that similar relief should apply to the renewable energy sector.
After examining the matter, MNRE clarified that the Standard Bidding Guidelines for procurement of renewable power — covering solar, wind, hybrid, and Firm and Dispatchable Renewable Energy (FDRE) — issued under Section 63 of the Electricity Act, 2003, already mandate that PPAs contain Force Majeure provisions aligned with industry standards. The advisory, therefore, directs agencies to apply these existing provisions rather than create a new blanket waiver.
Scope and Implications for the Sector
India's renewable energy pipeline is among the largest in the world, with hundreds of gigawatts under various stages of development. Supply disruptions originating in West Asia — a critical transit and manufacturing corridor for solar panels, inverters, and related components — have reportedly pushed commissioning timelines across multiple projects. This is not the first time geopolitical events have triggered Force Majeure relief for the sector; the Covid-19 pandemic prompted similar extensions in 2020 and 2021.
The extension is expected to provide breathing room to developers facing penalty clauses, while ensuring that India's renewable energy capacity addition targets are not permanently set back by a conflict outside their control. Agencies will now assess individual project requests against the 29 April 2026 Finance Ministry order to determine eligibility.