Is Madhya Pradesh Set to Boost Power Generation by 1320 MW?

Click to start listening
Is Madhya Pradesh Set to Boost Power Generation by 1320 MW?

Synopsis

Madhya Pradesh is on the brink of revolutionizing its energy landscape with the addition of 1320 MW of power in two thermal plants. This initiative not only enhances energy security but also showcases the state's commitment to sustainable development. Discover how this ambitious project is set to reshape the future energy dynamics of the region!

Key Takeaways

  • Madhya Pradesh to add 1320 MW of power.
  • Investment in ultra-supercritical technology enhances sustainability.
  • Project cost has risen to ₹11,671 crore.
  • Expected commissioning by 2030.
  • Environmental clearances obtained.

Bhopal, Sep 23 (NationPress) Madhya Pradesh is preparing for a significant upgrade in its energy framework by incorporating an additional 1320 MW of power into its existing thermal power facilities located in Sarni (Betul) and Chachai (Amarkantak).

The Madhya Pradesh Power Generating Company Limited (MPPGCL) has commenced the development of a 660 MW ultra-supercritical unit as part of Phase-V of the Satpura Thermal Power Project. This groundbreaking initiative is set to enhance the state's power surplus capabilities in response to growing industrial demands and population increases.

Initially launched in 2012, the project faced several delays due to changes in regulations and technology. Now, with the revival of advanced ultra-supercritical technology, the new unit is expected to provide improved efficiency and lower emissions.

The project's total estimated cost has risen to ₹11,671 crore, a reflection of inflation and enhanced specifications.

“Despite the escalated costs, the state government has reiterated its commitment to providing 15 percent funding without imposing any additional financial strain. The government’s contribution will be integrated into the loan structure, requiring only ₹66 crore more to finalize the financial plan,” stated Kailash Vijayvargiya, Urban Development Minister and government spokesperson, following a Cabinet meeting where the government decided to advance with the project.

The plant is expected to be operational by 2030, forming part of a comprehensive strategy to guarantee long-term energy security for Madhya Pradesh.

The Satpura expansion has acquired environmental approval from the Ministry of Environment, Forest and Climate Change, confirming its alignment with national sustainability benchmarks, as mentioned by the minister.

Simultaneously, another thermal power initiative worth ₹11,476 crore has been greenlit under similar conditions.

This project includes a 660 MW unit at Chachai, Amarkantak, bringing the total capacity of both projects to 1,320 MW.

Like the Satpura project, the Chachai unit will also utilize ultra-supercritical technology, improving efficiency and minimizing the carbon footprint, according to the minister.

These advancements signify a crucial step in Madhya Pradesh’s energy strategy. With both projects receiving support from the state and central governments, and designed to fulfill future industrial and residential energy needs, the state is positioning itself as a frontrunner in sustainable thermal power generation.

Point of View

The developments in Madhya Pradesh underscore a strategic commitment to enhancing energy infrastructure. The state aims to balance growing demand with sustainability, showcasing a forward-thinking approach that aligns with national energy goals.
NationPress
23/09/2025

Frequently Asked Questions

What is the total capacity being added in Madhya Pradesh?
Madhya Pradesh is adding a total of 1320 MW of power in its existing thermal plants.
What technology will be used in the new units?
The new units will utilize ultra-supercritical technology for improved efficiency and lower emissions.
What is the estimated cost of the new projects?
The total estimated cost for the projects is ₹11,671 crore and ₹11,476 crore respectively.
When is the plant expected to be operational?
The plant is scheduled to be commissioned by 2030.
Who has approved the environmental clearances?
The environmental clearances have been granted by the Ministry of Environment, Forest and Climate Change.
Nation Press