Meghalaya govt files FIR against KHADC inspector over Shillong ropeway site sealing
Synopsis
Key Takeaways
The Meghalaya government has lodged a formal complaint against an inspector of the Khasi Hills Autonomous District Council (KHADC) for allegedly sealing the lower terminal site of the proposed Shillong Peak Ropeway Project at Lawsohtun, officials confirmed on Thursday, 29 October 2026. The FIR was filed at Laban Police Station after the site was locked on Tuesday, triggering a fresh flashpoint in the long-running dispute over the project.
What the Government Said
Tourism Commissioner and Secretary R.M. Kurbah defended the project, stating that the land belongs to the government and that activities at the site were restricted to preparatory work. A temporary camp was being set up to facilitate soil testing, approach road development, and ground levelling, all in line with environmental and social safeguards prescribed by the New Development Bank, which is funding the project.
Kurbah clarified that construction had not commenced at either the lower terminal or at the proposed locations of the ropeway's six pillars. She also rejected allegations that work had begun without the requisite clearances, calling them factually incorrect.
Clearance Timeline and Due Process
According to Kurbah, the work order was issued to the contractor on 25 October 2025 following due procedure. The contractor obtained a no-objection certificate (NOC) from the Dorbar Pyllun on 4 May 2026 before applying for a KHADC trading licence on 18 May 2026.
The contractor subsequently sought an NOC from the Syiem of Hima Mylliem on 16 July, receiving a response on 28 July. The KHADC issued a show-cause notice on 27 August, which the contractor duly answered. A further NOC was obtained from the Dorbar Myntri of San Kur and 11 Kur of Riat Laban Mylliem on 28 September, even as the licensing process remained underway.
Kurbah added that the Meghalaya Infrastructure Development and Finance Corporation had consulted traditional institutions, including discussions with the Dorbars of Raid Laban and the lower terminal area as far back as 2022. She also addressed concerns over Lum Shyllong and its water catchment, noting that the site is approximately 3.15 km from the proposed ropeway location.
Opposition and Demands for Cancellation
Meanwhile, the Joint Action Committee opposing the project met the Syiem of Hima Mylliem on Wednesday, demanding cancellation of the sanads granted to headmen who entered into land lease arrangements for the project. The committee's intervention signals that community resistance remains organised and is now escalating through traditional governance channels.
No arrest had been made as of Thursday, with police confirming that an investigation into the sealing incident is underway.
What Happens Next
The FIR marks a significant escalation — a state government directly taking legal action against an autonomous council's functionary is rare in Meghalaya's governance landscape. The outcome of the police investigation, alongside the KHADC's licensing decision, is likely to determine whether preparatory work can resume or faces further legal hurdles. The project's financing from the New Development Bank adds an international dimension that could raise the stakes if delays persist.