Mizoram to get piped natural gas by 2028 via 119.45-km Indradhanush pipeline
Synopsis
Key Takeaways
Mizoram is set to receive piped natural gas (PNG) connections for domestic cooking by early 2028, as the Indradhanush Gas Grid Limited (IGGL) pushes ahead with a 119.45-km pipeline linking Panisagar in northern Tripura with Aizawl, officials confirmed on Monday, 26 October 2026. The project forms part of the broader Northeast Gas Grid Project, a ₹9,265 crore initiative to lay 1,656 km of natural gas pipelines across the northeastern states.
Ministerial Inspection and Project Status
Mizoram Food, Civil Supplies and Consumer Affairs Minister B. Lalchhanzova, accompanied by senior officials, visited Tuidam in Mamit district on Monday to inspect the ongoing pipeline work. The minister urged IGGL officials to accelerate construction and assured them of the Mizoram government's full cooperation in completing the project on schedule.
During the site visit, the minister also reviewed infrastructure challenges along the Tuidam approach road, where officials noted that several stretches along a 1.5-km section of the pipeline route require widening. IGGL and Public Works Department (PWD) officials held on-site discussions to coordinate their activities and ensure pipeline work does not interfere with existing road repair plans.
Timeline and Coverage
According to Minister Lalchhanzova, the connecting pipeline between Mizoram and the Tripura Natural Gas Company Limited (TNGCL) is being executed at an estimated cost of ₹491 crore. The project will initially cover Mamit and Aizawl districts. The pipeline is expected to reach Mamit town by March–April 2027 and Sihhmui in Aizawl district by March–April 2028.
Of the pipeline's total length, approximately 15.105 km will pass through six villages in Tripura, while the remaining 104.345 km will traverse 20 villages in Mizoram before reaching Aizawl. Once IGGL completes the main pipeline, TNGCL will begin providing PNG connections to households and commercial consumers in the two districts.
Why This Matters for Mizoram
The minister cited global conflicts and resulting energy supply disruptions as having caused periodic shortages of liquefied petroleum gas (LPG) in Mizoram, adversely affecting domestic cooking arrangements. Piped natural gas is seen as a more reliable and cleaner alternative, reducing the state's dependence on LPG cylinders sourced through long and disruption-prone supply chains.
Notably, Lalchhanzova also expressed hope that the availability of natural gas infrastructure could pave the way for Compressed Natural Gas (CNG) for vehicles in Mizoram, mirroring developments in other Indian states and helping reduce reliance on conventional liquid fuels.
About IGGL and the Northeast Gas Grid
IGGL is a joint venture promoted by Indian Oil Corporation Ltd (IOCL), Oil and Natural Gas Corporation (ONGC), GAIL (India) Ltd, Oil India Ltd (OIL), and Assam's Numaligarh Refinery Ltd (NRL). The Northeast Gas Grid is among the Centre's flagship energy connectivity projects for the region, aiming to integrate the eight northeastern states into India's national gas grid for the first time.
TNGCL, established on 10 July 1990, is a joint venture of GAIL (India) Ltd, Tripura Industrial Development Corporation Ltd, and Assam Gas Company Ltd. It currently supplies natural gas to domestic, commercial, industrial, and transport consumers across several districts of Tripura, and will serve as the upstream supplier once the Panisagar–Aizawl pipeline is commissioned.
With cross-departmental coordination underway and a clear phased timeline in place, Mizoram's transition from LPG dependency to piped gas infrastructure is expected to mark a significant shift in the state's energy landscape by 2028.