NHAI wins arbitration against Gujarat contractor's ₹174 crore claim, tribunal awards only ₹54 lakh

Share:
Audio Loading voice…
NHAI wins arbitration against Gujarat contractor's ₹174 crore claim, tribunal awards only ₹54 lakh

Synopsis

A contractor's ₹174.49 crore arbitration claim against NHAI over a Gujarat highway project ended with the Tribunal awarding just ₹54 lakh — less than 0.31% of the amount sought. The outcome, built on drone footage and digital project records, signals a new era of evidence-based contract accountability in Indian infrastructure.

Key Takeaways

NHAI won an arbitration case over the six-laning of the Kamrej–Chalthan section of NH-48 in Gujarat .
The Arbitral Tribunal awarded only ₹54 lakh against a contractor claim of ₹174.49 crore — a rejection of over 99.69% of the claimed amount.
The project was awarded to SCIW–Unique Construction (JV) in June 2016 at a bid cost of ₹241.41 crore and was foreclosed on 11 May 2020 at 49.79% physical progress.
NHAI's case relied on drone videography , digital project records, and technical documentation to counter the contractor's claims.
The contractor had expressly agreed not to raise future claims at the time of foreclosure in 2020 , but initiated arbitration in 2022 .

The National Highways Authority of India (NHAI) has won a significant arbitration case related to the six-laning of the Kamrej–Chalthan section of NH-48 in Gujarat, with the Arbitral Tribunal rejecting nearly the entirety of a ₹174.49 crore claim raised by the contractor. Against those claims, the Tribunal awarded just ₹54 lakh — less than one-third of one per cent of the amount sought — resulting in substantial savings of public funds, according to an official statement issued on Friday, 8 May 2025.

Background of the Project

The dispute centred on the widening of the 15-km Kamrej–Chalthan section of NH-48 from four lanes to six lanes, which also included long-term remedial measures for four black spots on the Kamrej–Bharuch corridor. The project was awarded in June 2016 to contractor SCIW–Unique Construction (JV) in engineering, procurement, and construction (EPC) mode at a bid cost of ₹241.41 crore. Work was formally scheduled to begin on 21 March 2017, with 87.75% land availability declared at the time.

How the Contract Fell Apart

During execution, the contractor repeatedly cited land-related constraints and demonstrated persistently slow progress, failing to meet contract provisions. Only basic road and drainage work was carried out; critical components including major structures and flyovers were never taken up. Owing to continued performance deficiencies, the contract was mutually foreclosed on 11 May 2020 at a physical progress of approximately 49.79%. At the time of foreclosure, both parties had agreed that all claims were fully and finally settled, and the contractor had expressly undertaken not to raise any future claims.

The Arbitration Challenge

Despite the foreclosure agreement, the contractor initiated arbitration proceedings in 2022, claiming approximately ₹174.49 crore from the NHAI — a move that was contrary to the terms of the settlement already signed. The NHAI contested the claims vigorously, presenting detailed documentary and digital evidence before the Arbitral Tribunal. This included drone videography, digital project records, and technical documentation demonstrating that sufficient land had been available for the six-laning works and that substantial drainage work had already been completed along the right of way. The evidence further established that the contractor had failed to undertake the key and challenging components of the project, which significantly contributed to the foreclosure.

Tribunal's Award and What It Signals

In its award dated 10 March 2025, the Arbitral Tribunal virtually rejected all claims made by the contractor. Against the ₹174.49 crore sought, the Tribunal awarded only ₹54 lakh to the claimant. The outcome underscores the critical role of digitisation and technology-driven project monitoring in infrastructure dispute resolution. Notably, this is among the most lopsided arbitration outcomes in recent NHAI history — with the contractor recovering less than 0.31% of its claimed amount.

NHAI's Broader Commitment

The NHAI stated that the result reflects its commitment to contractor accountability, prudent contract management, and protection of public funds. The authority added that robust documentation practices, including drone-based surveillance and digital records, are now integral to its project monitoring framework. The case is likely to serve as a precedent in future infrastructure arbitration proceedings involving state highway agencies, reinforcing the evidentiary weight of digital monitoring tools in contract disputes.

Point of View

Arbitration in highway contracts has been a backdoor for contractors to recover costs that poor execution or contractual breaches forfeited. NHAI's win here demonstrates that digital project monitoring is not just an operational tool — it is now a litigation weapon. The harder question is systemic: why was a project awarded at ₹241.41 crore foreclosed at barely 50% completion, and what does that say about contractor vetting and early-warning systems? The arbitration outcome is a victory, but the incomplete highway remains a cost that no tribunal award recovers.
NationPress
11 Aug 2026

Frequently Asked Questions

What was the NHAI arbitration case about?
The case involved a ₹174.49 crore claim raised by contractor SCIW–Unique Construction (JV) against NHAI over the six-laning of the 15-km Kamrej–Chalthan section of NH-48 in Gujarat. The Arbitral Tribunal awarded only ₹54 lakh, rejecting virtually all of the contractor's claims.
Why was the NH-48 Gujarat contract foreclosed?
The contract was mutually foreclosed on 11 May 2020 after the contractor demonstrated persistent slow progress, cited repeated land-related constraints, and failed to undertake critical components including major structures and flyovers. Physical progress stood at approximately 49.79% at the time of foreclosure.
How did NHAI win the arbitration case?
NHAI presented detailed digital evidence including drone videography, digital project records, and technical documentation showing that adequate land was available and that the contractor had not fulfilled key obligations. The Tribunal found this evidence compelling and rejected the bulk of the contractor's claims.
What did the contractor claim and what did it receive?
The contractor claimed approximately ₹174.49 crore from NHAI despite having agreed at the time of foreclosure in 2020 not to raise future claims. The Arbitral Tribunal, in its award dated 10 March 2025, granted only ₹54 lakh — less than 0.31% of the claimed amount.
What is the significance of this arbitration outcome for NHAI?
The outcome reinforces NHAI's use of digitisation and technology-driven monitoring as both a project management and legal tool. It is expected to serve as a precedent in future infrastructure contract disputes, strengthening contractor accountability and protecting public funds.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 2 weeks ago
  2. 2 months ago
  3. 2 months ago
  4. 4 months ago
  5. 4 months ago
  6. 8 months ago
  7. 1 year ago
  8. 1 year ago
Google Prefer NP
On Google