Ram Mandir construction 98% done, Parkota and lighting due by Nov 15: Nripendra Misra
Synopsis
Key Takeaways
Ram Mandir Construction Committee Chairman Nripendra Misra on Friday, 16 October, confirmed that 148 of approximately 150 construction works at the Ayodhya temple complex have been completed and handed over to the Ram Mandir Trust, with the remaining tasks set to conclude by 15 November. The update marks the final stretch of one of India's most closely watched infrastructure projects.
What Has Been Completed
Misra told reporters that construction firm L&T, which was tasked with executing the project, has been progressively handing over completed works to the Trust along with all relevant records, drawings, designs, and financial documentation. The Trust's own project engineers then conduct independent inspections before formally approving each handover.
Of the roughly 150 distinct works within the temple complex, 148 have cleared this handover process. The Martyrs' Memorial, another key component of the Ayodhya project, has also been fully completed. Misra noted he personally inspected it on Thursday, with only minor horticulture and landscaping work still pending at that site.
What Remains and Why
The principal outstanding task is the Parkota — the temple's perimeter enclosure structure. Misra explained that water treatment work on the Parkota's roof is still underway, and that continuous rainfall over the past three days in Ayodhya has slowed progress at the site. Lighting work across both the main temple and the Parkota is also ongoing.
'Of these 150 works, 148 have been completed and handed over. The major construction work that is yet to be handed over is the Parkota, the temple's perimeter structure,' Misra said. He added: 'Lighting work is currently underway in the temple and the Parkota. That will be completed by November 15.'
Madhavacharya Gate Progress
Misra also provided a separate update on the Madhavacharya Gate, stating that approximately 80 per cent of its construction has been finished. He said he was scheduled to inspect the site to assess further progress and identify any remaining gaps.
What Happens Next
With 15 November set as the firm deadline for all pending works — including the Parkota handover, lighting installations, and minor finishing tasks — the committee appears confident of a clean close-out before the winter festival season. The completion will mark the full structural and infrastructural handover of the Ram Mandir complex, nearly ten months after its consecration ceremony in January 2024. All eyes will now be on whether the November deadline holds amid unpredictable weather conditions at the site.