Synopsis
As of April 15, Nripendra Mishra, the Chairman of the Shri Ram Mandir Nirman Samiti, reported that 99% of Ram Mandir's construction is complete, with remaining works scheduled for completion by December 2025.Key Takeaways
- 99% construction completion of Ram Mandir.
- 2000 cubic stones yet to be placed.
- The Ram Darbar to be installed in May.
- Surrounding ramparts construction ongoing.
- Completion expected by December 2025.
Ayodhya, April 15 (NationPress) The Chairman of the Shri Ram Mandir Nirman Samiti, Nripendra Mishra, announced on Tuesday that an impressive 99 percent of the temple's construction is now finished. He mentioned that approximately 2,000 cubic stones are still required to be placed on either side of the temple, but no further stonework is necessary in the sanctum sanctorum.
During a media briefing, Mishra stated, “Discussions have taken place, and as you may have read or seen, we have entered the final phase of this project. The event held yesterday was particularly significant, coinciding with the birth anniversary of Dr B.R. Ambedkar, the esteemed architect of our Constitution. On this day, the principles of social harmony exemplified by Lord Ram, the Maryada Purushottam, were brought to life.”
Mishra disclosed that the temple’s ground, first, and second floors are all complete. “The Ram Darbar will be set up on the first floor in May. The trust will determine the schedule for the installation,” he noted.
He further added that efforts are ongoing to expedite the construction of the temple’s surrounding ramparts.
“Several new tasks have been initiated and must be finalized. The temporary offices on the northern side will be removed within the next three months. Landscaping and horticulture work will be conducted there as per the master plan, and the Northern Gate is nearing completion,” he elaborated.
According to Mishra, all construction activities related to the temple are anticipated to be concluded by December 2025.
Mishra also shared that on the occasion of Ambedkar Jayanti on Monday, all seven temples dedicated to significant figures from Lord Ram’s life -- Maharishi Valmiki, Nishad Raj, Shabari, Ahalya, Agastya Muni, and Vashishtha -- have been completed, and the idols have been delivered.
He also mentioned the completion of the Jaltal Pushkarni, a unique water tank located among the seven temples. “Upon its unveiling, a group of monkeys was seen bathing in it -- a joyous moment and a remarkable sight for everyone,” he remarked.
The temple’s shikhar (spire) is also 99 percent complete. “The kalash (urn) has been placed atop the peak, and another kalash for the parkota (temple perimeter) will be installed by April 30. The corresponding idols of gods and goddesses will also be gradually positioned,” he added.
Mishra acknowledged that there have been delays in the project and extended an apology.
He also announced that a statue of Goswami Tulsidas will be unveiled soon, allowing devotees to pay their respects. “Progress is also being made on the museum. If we manage to complete five galleries in the next three months, it will provide a new experience for visitors to the temple,” he said.