Ram Temple complex construction complete; formalities to close by December-end: Misra
Synopsis
Key Takeaways
The Ram Temple complex in Ayodhya has been fully constructed, with Ram Mandir Construction Committee Chairman Nripendra Misra confirming on Friday, 20 November 2026 that the remaining administrative and financial formalities — including financial closure and deductions — are on track to be wrapped up by the end of December. Misra made the announcement during a two-day review meeting of the construction committee in Ayodhya.
Construction Status and Quality Review
Misra confirmed that Larsen & Toubro (L&T), the principal construction contractor, has no major construction activity remaining at the complex. The committee reviewed construction quality in detail, and Engineers India Limited (EIL) and Tata Consulting Engineers (TCE) — the project monitoring agencies — have been tasked with assessing the quality of various structures within the complex.
The two-day meeting is also expected to cover matters related to the upcoming session of the Ram Temple Trust, which now holds operational and maintenance responsibility for the site.
Property Handed Over to the Trust
Misra said that, barring a few assets, the entire property has been handed over to the Ram Temple Trust. With the transfer largely complete, the Trust is now responsible for the day-to-day management and long-term upkeep of the temple complex. The focus for the construction committee has narrowed to completing financial settlements and administrative closures before the year ends.
Future of the Construction Committee
On the question of the committee's future, Misra was categorical: the body was constituted on the orders of the Supreme Court and will conclude its work accordingly. 'The committee was formed on the orders of the Supreme Court, so it will conclude here. Any future decision will be taken by the central and state governments, and if there is any judicial intervention, it will be carried out in accordance with the court's orders,' he said.
Misra also clarified attendance protocols, noting that members may participate physically or through virtual platforms. 'There has not been a single meeting that we have not attended virtually,' he said. The next meeting is scheduled for 2 December, and Misra indicated he would attend in person if his schedule permitted, failing which he would join virtually from Delhi.
What Happens Next
With construction finished and most assets transferred to the Trust, the committee's remaining mandate centres on financial closure — settling accounts with L&T, completing deductions, and formally winding down the construction oversight framework. All pending formalities are expected to be resolved before 31 December 2026, after which the committee's role will formally cease. The Ram Temple Trust will then assume full, undivided responsibility for one of India's most significant religious and cultural landmarks.