Guwahati JICA water supply projects near finish after 13 years, December 2025 deadline set

Share:
Audio Loading voice…
Guwahati JICA water supply projects near finish after 13 years, December 2025 deadline set

Synopsis

Started in 2012 with a 3-year deadline, Guwahati's JICA-funded water supply projects are only now nearing the finish line — 13 years later. With ₹1,450.87 crore spent and over 98,000 households in the pipeline, the December 2025 target is the city's best shot yet at closing a chronic drinking water gap for 2.21 lakh households.

Key Takeaways

Assam Minister Kaushik Rai told the Legislative Assembly on 9 July that Guwahati's JICA-funded water projects will be completed by December 2025 .
The South-Central Guwahati Water Supply Project is 96.75% complete; the North Guwahati project is at 95.75% .
Combined expenditure on the two JICA projects stands at ₹1,450.87 crore , with the full JICA loan utilised by December 2024 .
The South-Central project already serves 83,569 households ; the North Guwahati scheme will add roughly 15,000 more .
Surveys show Guwahati needs connections for 2.21 lakh households in total — highlighting the scale of remaining demand.
Three additional projects — South-West, South-East, and Zoo Road — are at varying stages, with completion targets between 2027 and 2029 .

Assam Housing and Urban Affairs Minister Kaushik Rai told the state Legislative Assembly on Thursday, 9 July that two long-delayed drinking water supply projects in Guwahati, funded by the Japan International Cooperation Agency (JICA), are on course for completion by December 2025 — more than a decade after construction began in March 2012. The disclosure came in response to a query raised by Congress MLA Rekibuddin Ahmed.

Current Progress on JICA-Funded Projects

The South-Central Guwahati Water Supply Project has achieved 96.75 per cent physical progress, while the North Guwahati Water Supply Project stands at 95.75 per cent completion, according to Minister Rai. Both projects were originally scheduled to wrap up within 36 months and 28 months of their respective start dates — timelines that were missed by several years.

A combined expenditure of ₹1,450.87 crore has been incurred on the two projects: ₹1,425.93 crore drawn from JICA assistance and ₹24.95 crore from the State-Owned Priority Development (SOPD) fund. The entire JICA loan component was utilised by December 2024, with residual works to be completed by end of 2026.

Households to Benefit

The South-Central Guwahati project is already supplying potable water to 83,569 households. The North Guwahati scheme, once fully operational, is expected to extend coverage to approximately 15,000 additional households. Surveys cited by the Minister indicate that Guwahati requires drinking water connections for roughly 2.21 lakh households in total, underscoring the scale of the unmet demand.

Other Water Supply Schemes Under Way

The Assembly was also informed about the status of three other ongoing projects. The South-West Guwahati Water Supply Project, being implemented by the Guwahati Jal Board since October 2023 at an estimated cost of ₹324.35 crore, has recorded 72 per cent progress and is scheduled for completion by mid-2027.

The South-East Guwahati Water Supply Project, backed by the New Development Bank (NDB), has completed 17 per cent of its first phase after work resumed in March 2025. The Asian Development Bank-supported initial phase had concluded in September 2021. The ₹192.46 crore project is targeted for completion by May 2029.

The Zoo Road Water Supply Scheme, commissioned in 1996 and transferred to the Guwahati Jal Board in 2015, has incurred expenditure of ₹75.39 crore and currently serves approximately 900 households.

Municipal Corporation Schemes and Sewerage Work

Beyond the Jal Board projects, the Guwahati Municipal Corporation operates water supply schemes at Panbazar, Satpukhuri, and Kamakhya. During the previous financial year, ₹3.52 crore was spent on these schemes, benefiting close to 21,000 consumers. Minister Rai also noted that the JICA-assisted Guwahati Sewerage Project is simultaneously in progress, adding another layer to the city's long-overdue urban infrastructure overhaul.

With multiple projects at advanced stages, the coming months will be a critical test of whether Guwahati can finally close the gap between its water supply capacity and the needs of its growing population.

Point of View

450 crore — a timeline failure that rarely gets the accountability scrutiny it deserves. The 96–97 per cent completion figures are encouraging, but Guwahati still needs connections for 2.21 lakh households against a patchwork of schemes with staggered deadlines stretching to 2029. The city's water crisis is not being solved in one go; it is being managed in instalments. What the Assembly debate did not surface is why the original deadlines slipped so dramatically, and whether the agencies responsible have been held to account.
NationPress
9 Jul 2026

Frequently Asked Questions

When will the JICA-funded water supply projects in Guwahati be completed?
According to Assam Housing and Urban Affairs Minister Kaushik Rai, both JICA-funded projects — the South-Central and North Guwahati Water Supply Projects — are expected to be completed by December 2025. Work on both projects began in March 2012.
How much has been spent on Guwahati's JICA water projects?
A total of ₹1,450.87 crore has been spent on the two projects — ₹1,425.93 crore from JICA assistance and ₹24.95 crore from the State-Owned Priority Development (SOPD) fund. The entire JICA loan component was utilised by December 2024.
How many households will benefit from the Guwahati water supply projects?
The South-Central Guwahati project is already supplying water to 83,569 households. The North Guwahati scheme is expected to cover around 15,000 additional households once fully operational. Surveys indicate the city needs connections for about 2.21 lakh households in total.
What other water supply projects are under way in Guwahati?
Three other projects are ongoing: the South-West Guwahati Water Supply Project (72% complete, target mid-2027), the South-East Guwahati Water Supply Project (17% of first phase, target May 2029), and the Zoo Road Water Supply Scheme, which currently serves around 900 households.
Why were the Guwahati water projects delayed?
The projects, which started in March 2012, were originally due for completion within 28–36 months but have experienced significant delays over more than a decade. Minister Rai acknowledged the delays in the Assembly but did not detail the specific reasons on the floor of the House.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 1 week ago
  2. 2 weeks ago
  3. 1 month ago
  4. 1 month ago
  5. 1 month ago
  6. 1 month ago
  7. 5 months ago
  8. 1 year ago
Google Prefer NP
On Google