BMC gets Maharashtra nod for 8-km underground water tunnel in Bhiwandi
Synopsis
Key Takeaways
The Maharashtra government on Monday, 21 September 2026, granted formal approval to the Brihanmumbai Municipal Corporation (BMC) to design and construct an 8-kilometre underground water tunnel linking Pise and Panjrapur in Bhiwandi, a critical step toward securing the Mumbai Metropolitan Region's (MMR) long-term water supply infrastructure.
Why the Tunnel Is Needed
The same 8-km stretch is currently served by four surface pipelines — three measuring 2,235 mm in diameter and one measuring 3,000 mm — commissioned between 1979 and 2007. Having operated for 47, 40, 30, and 19 years respectively across Stages 1, 2, 3, and 3A, the pipelines are nearing the end of their operational lifespan.
The transition to an underground tunnel addresses mounting challenges: space constraints along the existing pipeline corridor in Bhiwandi, structural deterioration of ageing infrastructure, vulnerability to surface disruptions, escalating water demand across the MMR, and the need to integrate with newly planned pumping stations and ongoing network-strengthening projects.
How the Approval Came About
The BMC's Additional Municipal Commissioner formally moved the proposal by letter dated 23 March 2026, seeking state clearance to commence pre-construction and engineering preparations. The Maharashtra government's approval, extended on Monday, clears the path for detailed project design and construction planning.
Conditions the State Has Imposed
The state has made clear that the project carries zero financial liability for the government — the BMC alone is responsible for funding, execution, and long-term maintenance. Key conditions include ensuring no damage to buildings or structures along the tunnel route, verifying whether clearances from the Ministry of Environment or the Groundwater Survey and Development Agency are required, and obtaining permissions from the Ministry of Environment, Forest and Climate Change (MoEF&CC) and other relevant authorities.
Authorities also directed that the Tunnel Boring Machine (TBM) be selected only after a thorough geological study of the underground strata. The state stressed that 'necessary measures must be taken to ensure that no disaster-like situation arises during the ongoing work or after completion of the water tunnel due to heavy rainfall in Mumbai and adjacent areas during the monsoon period.'
Environmental and Safety Safeguards
The BMC must safely dispose of solid waste generated during excavation and implement measures to prevent dust pollution. Noise-control requirements are strict: the civic body must deploy silencers, sound barriers, rubber mats for muck-handling trucks, and hydraulically operated crane hoisting systems to keep noise levels below 55 decibels.
The BMC will bear full responsibility for preservation, maintenance, repairs, and all legal, judicial, or administrative issues arising from excavation or construction. With approvals now in motion and geological studies required before TBM selection, the project's timeline will hinge on how swiftly the BMC clears environmental and regulatory hurdles.