The megawatt number has been misleading people — and Arunachal Pradesh Chief Minister Pema Khandu wants to correct the record. In a pointed explainer posted on Wednesday, 30 September 2026, Khandu broke down why India's proposed 11,000 MW Siang Upper Multipurpose Project (SUMP) can still moderate floodwaters from a Chinese dam rated at nearly six times the power capacity, using a single, decisive distinction: storage volume beats megawatt count every time.
MW versus BCM: the number that actually matters for flood control
Khandu's post cuts straight to the engineering reality. China's Medog project on the Yarlung Tsangpo in Tibet is reported to carry roughly 5.5 Billion Cubic Metres (BCM) of storage. SUMP, despite its far lower power rating, is designed for 9.2 BCM of live storage — nearly 1.7 times the water-holding capacity of the upstream Chinese project. That margin is precisely what gives India a structural lever over downstream flood peaks, irrespective of how many turbines sit on either side of the border.
The reason the Medog project generates such colossal power, Khandu explains, is pure geography. The Yarlung Tsangpo Great Bend — a dramatic gorge in Tibet where the river drops thousands of metres in a short horizontal distance — hands Chinese engineers an extraordinary hydraulic head. More elevation drop means more power from the same volume of water. 'More MW does not mean more stored water,' Khandu wrote, and in four words he closes the argument that has stumped many commentators.
Dibang Valley projects make the same point closer to home
To make the abstraction concrete, Khandu pointed to two projects in Arunachal Pradesh's Dibang Valley that sit side by side. The proposed Etalin Hydropower Project is designed to generate 3,097 MW but holds a mere 7.5 Million Cubic Metres (MCM) of storage — essentially a run-of-river scheme that converts flow to electricity without retaining it. The Dibang Multipurpose Project, by contrast, is rated at 2,880 MW — actually lower than Etalin — yet carries roughly 4 BCM of storage, making it a genuine reservoir that can buffer seasonal surges. Same river basin, wildly different flood-moderation value. The comparison is hard to argue with.
Why India has been building the storage case for years
India's concern about upstream Chinese dams on the Brahmaputra system has been a recurring thread in bilateral water-resources diplomacy since the 2000s, when Beijing began announcing large-scale hydropower ambitions on the Yarlung Tsangpo. The worry is straightforward: a dam upstream can withhold water during dry seasons and, critically, release sudden surges that devastate downstream communities in Arunachal Pradesh and Assam.
SUMP has been positioned in Indian technical circles as the answer — a high-storage reservoir that could absorb an abnormal release from Tibet before it hits the plains. Khandu's post is, in effect, a public-education campaign for a project that has faced scrutiny over the apparent mismatch between its modest power rating and the scale of the geopolitical task assigned to it. By walking through the BCM arithmetic in plain language, the Chief Minister is making the case that the engineers got it right — and that the critics have been reading the wrong number.
Clearances and investment decisions for SUMP remain in progress. But the intellectual groundwork, Khandu is signalling, is already settled.