Railway Board Chairman reviews safety, KAVACH rollout in high-level meet

Share:
Audio Loading voice…
Railway Board Chairman reviews safety, KAVACH rollout in high-level meet

Synopsis

Railway Board Chairman Satish Kumar's nationwide review meeting on 19 September put the spotlight on Kavach 4.0 — already live on 1,210 km of the Delhi-Howrah corridor — with ₹223.83 crore sanctioned for 443 km more in West Bengal. The session signals that India's indigenous train-protection rollout is accelerating, but the real test lies in covering the remaining high-density stretches on time.

Key Takeaways

Railway Board Chairman Satish Kumar chaired a high-level safety review meeting on 19 September 2026 via video conference with all zonal general managers.
Kavach 4.0 has been deployed across 1,210 route km on the Delhi-Howrah high-density corridor; work on remaining stretches is ongoing.
The Ministry of Railways earlier approved Kavach installation over 443 route km in West Bengal at an estimated cost of ₹223.83 crore .
Eastern Railway GM Gitika Pandey presented ER's safety performance, highlighting CCTV expansion, level crossing interlocking, and signalling modernisation.
Infrastructure progress reviewed included ROBs , RUBs , track maintenance, and waterlogging remediation at subways and Limited Height Subways .
Officials from South Eastern Railway and Metro Railway also participated, presenting project status updates.

Railway Board Chairman and CEO Satish Kumar on Saturday, 19 September 2026, chaired a high-level review meeting to assess safety in train operations and key infrastructure works across Indian Railways' zonal network. General managers and principal heads of departments from all railway zones participated via video conference, making it one of the most comprehensive periodic safety reviews conducted at the national level.

Eastern Railway in focus

Eastern Railway (ER) General Manager Gitika Pandey attended alongside divisional railway managers and principal heads of departments, presenting the zone's safety performance status and the progress of safety-critical works. Pandey highlighted a clutch of major initiatives: strengthening the safety management framework, expanding CCTV surveillance, progressively eliminating and interlocking level crossing gates, and modernising signalling systems through the replacement and upgradation of mechanical lever frames and panel interlocking installations.

KAVACH Rollout on Delhi-Howrah Route

The review gave considerable attention to KAVACH, the indigenous Automatic Train Protection (ATP) system developed by Indian Railways. The latest iteration, Kavach 4.0, has been successfully deployed across 1,210 route km on the high-density Delhi-Howrah corridor, with work actively underway to cover the remaining stretches. The system is also being progressively inducted into locomotives.

Earlier this year, the Ministry of Railways approved the installation of Kavach across 443 route km in West Bengal at an estimated cost of ₹223.83 crore. Several suburban sections in the state are being brought under this safety net, signalling a push to extend protection beyond inter-city trunk routes.

Infrastructure and Passenger Amenity Works

The meeting also covered infrastructure development and passenger amenity improvements over the ER network. Discussions included comprehensive track maintenance, progress on Road Over Bridges (ROBs) and Road Under Bridges (RUBs), and engineering measures to address waterlogging at identified subways and Limited Height Subways (LHSs). While appreciating ER's systematic approach to execution and monitoring, Kumar emphasised sustained attention to safety, timely project completion, and adoption of modern technology.

What Officials Said

'Safety remains the foremost priority in every aspect of railway operations. ER is continuously strengthening safety systems, accelerating technological upgrades such as KAVACH and modern signalling, and improving infrastructure to ensure safer, more reliable and passenger-friendly train operations,' said Shibram Majhi, Chief Public Relations Officer (CPRO), Eastern Railway.

Officials noted that these periodic review meetings by the Chairman and CEO of the Railway Board are designed to sharpen zonal efforts toward safer train operations, improved reliability, and better passenger services. Representatives from South Eastern Railway and Metro Railway also participated and presented the status of various projects in their respective jurisdictions.

The reviews are expected to continue at regular intervals, with the next meeting likely to track milestone completion on Kavach expansion and the ROB-RUB construction pipeline across zones.

Point of View

210 km of the Delhi-Howrah corridor marks a meaningful milestone for a system that spent years in pilot mode. Yet the coverage gap on the remaining Delhi-Howrah stretches — and the broader national network — remains vast. The ₹223.83 crore West Bengal sanction sounds substantial but covers only 443 km in a country with over 68,000 route km. Periodic review meetings are useful for accountability, but the pace of Kavach induction will ultimately be the metric by which this safety push is judged, not the frequency of high-level video calls.
NationPress
19 Sept 2026

Frequently Asked Questions

What was discussed at the Railway Board Chairman's safety review meeting on 19 September 2026?
The meeting, chaired by Railway Board Chairman and CEO Satish Kumar, reviewed train safety performance, the progress of KAVACH implementation, infrastructure works including ROBs and RUBs, track maintenance, and passenger amenity improvements across all railway zones. General managers and principal heads of departments from every zone participated via video conference.
What is Kavach and how far has it been implemented on the Delhi-Howrah route?
Kavach is an indigenous Automatic Train Protection (ATP) system developed by Indian Railways to prevent train collisions by automatically applying brakes. Kavach 4.0 has been successfully implemented on 1,210 route km of the high-density Delhi-Howrah corridor, with work underway to cover the remaining stretches.
How much has the government sanctioned for Kavach installation in West Bengal?
The Ministry of Railways approved the installation of Kavach across 443 route km in West Bengal at an estimated cost of ₹223.83 crore. Several suburban sections in the state are being brought under the Kavach safety net as part of this approval.
What safety initiatives did Eastern Railway General Manager Gitika Pandey highlight?
Gitika Pandey highlighted expanding CCTV surveillance, progressively eliminating and interlocking level crossing gates, and modernising signalling systems through replacement and upgradation of mechanical lever frames and panel interlocking installations, in addition to the Kavach rollout.
Which other railway zones participated in the review meeting?
Apart from Eastern Railway, representatives from South Eastern Railway and Metro Railway also participated in the meeting and presented the status of their respective projects. General managers and principal heads from all railway zones attended via video conference.
Nation Press
The Trail

Connected Dots

Tracing the thread behind this story — newest first.

8 Dots
  1. Latest 6 hours ago
  2. 2 weeks ago
  3. 1 month ago
  4. 3 months ago
  5. 3 months ago
  6. 6 months ago
  7. 7 months ago
  8. 9 months ago
Google Prefer NP
On Google